926 N SYCAMORE AVE 700 90038
Certificate Information: 926 N SYCAMORE AVE 700 90038
- Application / Permit
- 22016-10000-27566
- Plan Check / Job No.
- B22LA18370
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EPLAN INTERIOR TI OF EXISTING OFFICE SPACE INCLUDING NEW PARTITIONS, MILLWORK, AND DOORS. EXISTING 'B' OCCUPANCY TO REMAIN, NO CHANGE OF USE OR AREA. Existing suite 700: 9,792 USF (scope of work)
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/28/2023
Permit Application Status History
| Submitted | 9/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | ZAW HAN |
| Corrections Issued | 9/16/2022 | ZAW HAN |
| Plan Check Approved | 10/11/2022 | ZAW HAN |
| Issued | 2/21/2023 | APPLICANT |
| Permit Finaled | 8/21/2023 | JEROME BLACKWOOD |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Wilder,, Arthur J; Lic. No.: NA27915 | , |
| Contractor | Turelk Inc; Lic. No.: 372562-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 3/29/2023 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 4/4/2023 | Approved | JEROME BLACKWOOD |
| Drywall Nailing | 4/19/2023 | Partial Approval | JEROME BLACKWOOD |
| T-Bar Ceiling | 6/7/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| T-Bar Ceiling | 6/8/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 6/16/2023 | Partial Approval | MARTIN TAVITIAN |
| T-Bar Ceiling | 6/16/2023 | Partial Approval | MARTIN TAVITIAN |
| Drywall Nailing | 6/22/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 6/26/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 6/28/2023 | Partial Approval | RAFAEL CORTES |
| Final | 8/18/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Not Ready | RONALD JIMENEZ |
| Smoke Detectors | 8/18/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 8/21/2023 | Permit Finaled | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 8/21/2023 | Approved | JEROME BLACKWOOD |