3823 W SUNSET BLVD 90026
Certificate Information: 3823 W SUNSET BLVD 90026
- Application / Permit
- 22016-10000-27553
- Plan Check / Job No.
- B22LA18362
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Change of use of portion of the building from Retail to restaurant. Tenant improvements of an existing restaurant space to be converted into a Salt and Straw Ice-cream parlor.
- Permit Issued
- Issued on 1/9/2023
- Issuing Office
- Current Status
- Issued on 1/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | SALVADOR QUINTANILLA |
| Corrections Issued | 10/2/2022 | SALVADOR QUINTANILLA |
| Quality Review Completed | 10/4/2022 | PETER KIM |
| Applicant returned to address corrections | 12/12/2022 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 12/15/2022 | SALVADOR QUINTANILLA |
| Plan Check Approved | 1/6/2023 | SALVADOR QUINTANILLA |
| Issued | 1/9/2023 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/18/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 10/18/2022 | RUBEN VASQUEZ |
| Comm Cor/Mini-Mall | Cleared | 10/20/2022 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 11/7/2022 | CHRISTOPHER ROCHA |
| Food Service Establishment | Cleared | 11/22/2022 | KENNETH BROWNE |
| Food establishment approval | Cleared | 12/15/2022 | LACDHS APPROVED |
| DAS Clearance | Cleared | 12/20/2022 | Jesse Jimenez |
Contact Information
| Architect | Gerdes,, F Andrew; Lic. No.: NA17261 | , |
| Contractor | Willis A R Construction Inc; Lic. No.: 1020831-B | , |
| Engineer | Alam,, Anwar; Lic. No.: NA5719 | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 2/2/2023 | Conditional Approval | MARTIN TAVITIAN |
| Drywall Nailing | 2/10/2023 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 2/15/2023 | Approved | GREGORY POMISH |
| T-Bar Ceiling | 2/23/2023 | Approved | JULIAN CAPUCETTI |
| Final | 3/30/2023 | Partial Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 3/30/2023 | Approved | TIMOTHY POWELL |
| Final | 4/7/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 4/7/2023 | SGSOV Approved | TIMOTHY POWELL |