4700 S INGLEWOOD BLVD 90230
Certificate Information: 4700 S INGLEWOOD BLVD 90230
- Application / Permit
- 22016-10000-27509
- Plan Check / Job No.
- B22LA18317
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- ePLAN. TI in existing market for new floor plan layout. New equipment at roof. No change in building footprint nor parking spaces.
- Permit Issued
- Issued on 4/18/2023
- Issuing Office
- Current Status
- Permit Finaled on 5/10/2024
Permit Application Status History
| Submitted | 9/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | TU HUA |
| Corrections Issued | 9/21/2022 | TU HUA |
| Quality Review Completed | 9/27/2022 | CHAD DOI |
| Applicant returned to address corrections | 3/29/2023 | TU HUA |
| Plan Check Approved | 4/10/2023 | TU HUA |
| Issued | 4/18/2023 | APPLICANT |
| Permit Finaled | 5/10/2024 | JOEY BUCHANAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2022 | JENSON LEE |
| Comm Cor/Mini-Mall | Cleared | 11/17/2022 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 11/17/2022 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 11/17/2022 | SPENCER WEJROWSKI |
| "Q" conditions | Cleared | 12/5/2022 | SPENCER WEJROWSKI |
| Comm Cor/Mini-Mall | Cleared | 12/5/2022 | SPENCER WEJROWSKI |
| Comm Cor/Mini-Mall | Cleared | 12/5/2022 | SPENCER WEJROWSKI |
| Food Service Establishment | Cleared | 1/17/2023 | KENNETH BROWNE |
| ZA Case | Cleared | 1/18/2023 | RICARDO MARTINEZ |
| ZA Case | Cleared | 1/18/2023 | RICARDO MARTINEZ |
| Sewer availability | Cleared | 2/2/2023 | DINAH GARIN |
| Green Code | Cleared | 2/6/2023 | Jesse Jimenez |
| Specific Plan | Cleared | 3/1/2023 | EDUARDO HERMOSO |
| DAS Clearance | Cleared | 3/5/2023 | Jesse Jimenez |
| Food establishment approval | Cleared | 4/10/2023 | LACDHS APPROVED |
Contact Information
| Architect | Blankenship,, Mitchell Lee; Lic. No.: C16811 | 691 BLACKBURN AVENUE FAIRFIELD, OH 45014 |
| Contractor | Savant Construction Inc; Lic. No.: 596646-B | , |
| Engineer | Khamsi,, Ali; Lic. No.: C74768 | 124 VIA UNDINE NEWPORT BEACH, CA 92663 |
| Engineer | Leonard,, Joseph Kristian; Lic. No.: S2969 | 106 W LIME STE 206B MONROVIA, CA 91016 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/20/2023 | Not Ready for Inspection | GRANT WOODS |
| Pre-Inspection | 6/20/2023 | Partial Inspection | GRANT WOODS |
| Light Gage Steel Frame | 6/27/2023 | Not Ready for Inspection | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Not Ready for Inspection | GRANT WOODS |
| Light Gage Steel Frame | 6/29/2023 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 6/30/2023 | Partial Approval | MICHAEL PETRUSKO |
| Light Gage Steel Frame | 7/5/2023 | Not Ready for Inspection | GRANT WOODS |
| Light Gage Steel Frame | 7/12/2023 | Partial Approval | GRANT WOODS |
| T-Bar Ceiling | 7/12/2023 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 7/13/2023 | Partial Approval | GRANT WOODS |
| T-Bar Ceiling | 7/13/2023 | Partial Inspection | GRANT WOODS |
| Drywall Nailing | 7/17/2023 | Partial Inspection | GRANT WOODS |
| Drywall Nailing | 7/18/2023 | Partial Approval | GRANT WOODS |
| Wood Frame | 7/20/2023 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 7/25/2023 | Not Ready for Inspection | GRANT WOODS |
| Deputy Drilled-In Anchors | 7/26/2023 | Conditional Approval | GRANT WOODS |
| Wood Frame | 7/26/2023 | Not Ready for Inspection | GRANT WOODS |
| Deputy Drilled-In Anchors | 7/27/2023 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 7/28/2023 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 8/1/2023 | Partial Inspection | ALAN NOVAK |
| Drywall Nailing | 8/2/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Grading Pre-Inspection | 8/2/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Drywall Nailing | 8/4/2023 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 8/4/2023 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 8/8/2023 | Corrections Issued | GRANT WOODS |
| Drywall Nailing | 8/14/2023 | Partial Inspection | GRANT WOODS |
| Light Gage Steel Frame | 8/14/2023 | Not Ready for Inspection | GRANT WOODS |
| Light Gage Steel Frame | 8/18/2023 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 8/21/2023 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 8/22/2023 | Corrections Issued | GRANT WOODS |
| Masonry Wall/Backfill | 8/22/2023 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 8/23/2023 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 8/24/2023 | Partial Approval | GRANT WOODS |
| T-Bar Ceiling | 8/28/2023 | Not Ready for Inspection | GRANT WOODS |
| Light Gage Steel Frame | 9/5/2023 | Partial Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 9/18/2023 | Not Ready for Inspection | GRANT WOODS |
| T-Bar Ceiling | 9/22/2023 | Partial Inspection | AMANUEL BERHE |
| T-Bar Ceiling | 9/26/2023 | Partial Approval | DAVID TSAU |
| Drywall Nailing | 9/28/2023 | Partial Inspection | GRANT WOODS |
| Light Gage Steel Frame | 9/28/2023 | Partial Approval | DAVID TSAU |
| Structural Steel Frame | 9/28/2023 | Partial Approval | DAVID TSAU |
| T-Bar Ceiling | 9/28/2023 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 9/29/2023 | Partial Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 10/2/2023 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 10/2/2023 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 10/3/2023 | Corrections Issued | GRANT WOODS |
| Deputy Reinf. Concrete | 10/4/2023 | Conditional Approval | GRANT WOODS |
| Drywall Nailing | 10/5/2023 | Partial Approval | GRANT WOODS |
| Footing/Foundation/Slab | 10/5/2023 | Partial Approval | GRANT WOODS |
| T-Bar Ceiling | 10/5/2023 | Not Ready for Inspection | GRANT WOODS |
| Final | 10/10/2023 | Partial Inspection | GRANT WOODS |
| Green Building Final | 10/10/2023 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 10/10/2023 | Not Ready for Inspection | GRANT WOODS |
| Special/Order Compliance | 10/12/2023 | Not Ready for Inspection | GRANT WOODS |
| T-Bar Ceiling | 10/12/2023 | Not Ready for Inspection | GRANT WOODS |
| Special/Order Compliance | 10/13/2023 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 10/18/2023 | Not Ready for Inspection | GRANT WOODS |
| Deputy Reinf. Concrete | 10/20/2023 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 10/26/2023 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 10/30/2023 | Partial Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 11/1/2023 | Approved | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 11/1/2023 | Partial Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 11/2/2023 | Conditional Approval | GRANT WOODS |
| Drywall Nailing | 11/3/2023 | Partial Approval | DAVID TSAU |
| Special/Order Compliance | 11/3/2023 | Partial Approval | GRANT WOODS |
| T-Bar Ceiling | 11/3/2023 | Not Ready for Inspection | DAVID TSAU |
| Wood Frame | 11/3/2023 | Partial Approval | DAVID TSAU |
| Drywall Nailing | 11/6/2023 | Partial Approval | NICK LAROCCA |
| Light Gage Steel Frame | 11/7/2023 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 11/8/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 11/8/2023 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 11/9/2023 | Not Ready for Inspection | DAVID TSAU |
| Light Gage Steel Frame | 11/9/2023 | Not Ready for Inspection | DAVID TSAU |
| Wood Frame | 11/9/2023 | Partial Approval | DAVID TSAU |
| Drywall Nailing | 11/13/2023 | Not Ready for Inspection | GRANT WOODS |
| Light Gage Steel Frame | 11/13/2023 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 11/15/2023 | Not Ready for Inspection | GRANT WOODS |
| T-Bar Ceiling | 11/20/2023 | Partial Inspection | DAVID TSAU |
| T-Bar Ceiling | 11/29/2023 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 12/5/2023 | Approved | DAVID TSAU |
| Final | 12/15/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Green Building Final | 12/15/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 12/15/2023 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 12/15/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 1/26/2024 | Not Ready for Inspection | GRANT WOODS |
| Green Building Final | 1/26/2024 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 1/26/2024 | Approved | GRANT WOODS |
| Final | 3/15/2024 | Not Ready for Inspection | GRANT WOODS |
| Final | 4/2/2024 | Not Ready for Inspection | GRANT WOODS |
| Final | 5/10/2024 | Permit Finaled | JOEY BUCHANAN |