12492 W GILMORE AVE 90066

Certificate Information: 12492 W GILMORE AVE 90066

Application / Permit
22016-10000-27367
Plan Check / Job No.
B22LA18222
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: By adding 1 Ordinary Moment frame at North elevation
Permit Issued
Issued on 1/17/2023
Issuing Office
Current Status
CofC Issued on 10/30/2023

Permit Application Status History

Submitted 10/4/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 HANS SANTIAGO
Corrections Issued 10/31/2022 HANS SANTIAGO
Quality Review Completed 10/31/2022 LIPING TENG
Plan Check Approved 11/21/2022 ANDREW SANTIAGO
Issued 1/17/2023 APPLICANT
OK for CofC 10/26/2023 MICHAEL PETRUSKO
CofC Issued 10/30/2023 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Tenant Habitability Plan Cleared 1/17/2023 RICARDO BOHORQUEZ

Contact Information

Contractor Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B       ,
Contractor Sks Construction; Lic. No.: 720390-B       ,
Engineer Shaolian,, Shahab Joseph; Lic. No.: C84155 15134 FRIAR ST      VAN NUYS, CA 91411

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/19/2023 Approved MICHAEL PETRUSKO
Deputy Steel/Welding 8/15/2023 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 8/22/2023 Partial Approval MICHAEL PETRUSKO
Footing/Foundation/Slab 8/24/2023 Approved MICHAEL PETRUSKO
Wood Frame 8/24/2023 Approved MICHAEL PETRUSKO
Deputy Reinf. Concrete 8/25/2023 Approved MICHAEL PETRUSKO
Interior/Exterior Lathing 9/27/2023 Approved MICHAEL PETRUSKO
Final 10/26/2023 OK for CofC MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Approved MICHAEL PETRUSKO
Smoke Detectors 10/26/2023 Approved MICHAEL PETRUSKO