7118 W 91ST ST 90045

Certificate Information: 7118 W 91ST ST 90045

Application / Permit
22016-10000-27336
Plan Check / Job No.
B22LA18201
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET GARAGE INTO (N) 26' X 20' ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/1/2023
Issuing Office
Current Status
CofO Issued on 7/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2022 APPLICANT
Assigned to Plan Check Engineer 9/12/2022 LUISANGEL VALENZUELA
Corrections Issued 9/13/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/30/2022 LUISANGEL VALENZUELA
Plan Check Approved 11/13/2022 HERNAN ARREOLA
Issued 2/1/2023 APPLICANT
CofO in Progress 7/2/2024 HERBERT GIRON
Permit Finaled 7/6/2024 DANIEL ORRANTE
CofO Issued 7/6/2024 DANIEL ORRANTE
Permit Finaled 7/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 9/15/2022 JENSON LEE
Grading Pre-Inspection Cleared 9/21/2022 KIRK LINKLATER
Address approval Cleared 9/22/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 9/22/2022 JENSON LEE
Construction near power lines Cleared 11/2/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/8/2023 Approved BOBBY KEY
Footing/Foundation/Slab 2/8/2023 Approved BOBBY KEY
Sewer 2/8/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 4/17/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Not Ready for Inspection BOBBY KEY
HVAC-Rough 4/17/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 4/17/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 4/21/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 4/21/2023 Approved BOBBY KEY
HVAC-Rough 4/21/2023 Approved BOBBY KEY
PLUMBING-Rough 4/21/2023 Approved BOBBY KEY
Special/Order Compliance 4/24/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 4/27/2023 Corrections Issued BOBBY KEY
Green Building Rough 4/27/2023 Corrections Issued BOBBY KEY
Insulation 4/27/2023 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 4/27/2023 Not Ready for Inspection BOBBY KEY
Sewer 5/4/2023 Approved BOBBY KEY
Pre-Inspection 5/12/2023 Partial Inspection BOBBY KEY
BUILDING-Rough-Frame 5/24/2023 Corrections Issued BOBBY KEY
Green Building Rough 5/24/2023 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 5/24/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Corrections Issued BOBBY KEY
Underground Mechanical 6/13/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 6/20/2023 Approved BOBBY KEY
Green Building Rough 6/20/2023 Approved BOBBY KEY
Underground Mechanical 6/20/2023 Partial Approval BOBBY KEY
ELECTRICAL-Final 6/30/2023 Corrections Issued BOBBY KEY
Insulation 6/30/2023 Approved BOBBY KEY
Drywall Nailing 7/10/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 4/18/2024 No Access for Inspection RICHARD STEINBACH
ELECTRICAL-Final 4/24/2024 Corrections Issued RICHARD STEINBACH
ELECTRICAL-Final 6/5/2024 No Access for Inspection HERBERT GIRON
ELECTRICAL-Final 6/7/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Final 6/11/2024 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Not Ready HERBERT GIRON
Drywall Nailing 6/24/2024 Approved HERBERT GIRON
ELECTRICAL-Final 6/24/2024 Approved HERBERT GIRON
Final 6/24/2024 Corrections Issued HERBERT GIRON
HVAC-Final 6/24/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 6/24/2024 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 6/24/2024 Approved HERBERT GIRON
Special/Order Compliance 6/24/2024 Partial Inspection TEMISTOCLES CAAL
Final 7/1/2024 OK to Issue CofO HERBERT GIRON
Green Building Final 7/1/2024 Approved HERBERT GIRON
HVAC-Final 7/1/2024 Approved HERBERT GIRON
PLUMBING-Final 7/1/2024 Approved HERBERT GIRON
Service/Power Release 7/1/2024 Approved HERBERT GIRON
Special/Order Compliance 7/1/2024 Partial Inspection TEMISTOCLES CAAL