2702 S SELBY AVE 90064
Certificate Information: 2702 S SELBY AVE 90064
- Application / Permit
- 22016-10000-26960
- Plan Check / Job No.
- B22LA17871
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING OF THE EXISTING 1-STORY RECREATION ROOM INTO A.D.U. WITH PROPOSED 2ND FLOOR ABOVE (E) GARAGE AND RECROOM WITHIN (E) BUILDING ENVELOPE. "COMPLY WITH DEPARTMENT ORDER effective date 03/30/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2022 | JOSEPH RAFOLS |
| Corrections Issued | 9/12/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 9/15/2022 | APPLICANT |
| Applicant returned to address corrections | 10/21/2022 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/2/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 5/24/2023 | MINA HABILI |
| Plan Check Approved | 6/2/2023 | CRISTINA SALAZAR |
| Issued | 6/2/2023 | APPLICANT |
| CofO in Progress | 10/24/2023 | ROBERT CHAVEZ |
| Permit Finaled | 11/15/2023 | DANIEL SANCHEZ |
| CofO Issued | 11/15/2023 | DANIEL SANCHEZ |
| Permit Finaled | 11/15/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 9/23/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 10/4/2022 | KYLE WINSTON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Quintanar,, Rudolph; Lic. No.: C37057 | 11465 SIVINTON AVE GRANADA HILLS, CA 91344 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/13/2023 | Partial Inspection | JOHN TCHANG |
| Pre-Inspection | 6/21/2023 | Partial Inspection | RUBEN PEREZ |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | ROBERT CHAVEZ |
| FLOOD-Proofing Certificate | 9/28/2023 | Approved | ROBERT CHAVEZ |
| Final | 9/28/2023 | OK to Issue CofO | ROBERT CHAVEZ |
| Footing/Foundation/Slab | 9/28/2023 | Approved | ROBERT CHAVEZ |
| Green Building Final | 9/28/2023 | Approved | ROBERT CHAVEZ |
| Green Building Rough | 9/28/2023 | Approved | ROBERT CHAVEZ |
| Smoke Detectors | 9/28/2023 | Approved | ROBERT CHAVEZ |