633 W 5TH ST 67TH FL 90071

Certificate Information: 633 W 5TH ST 67TH FL 90071

Application / Permit
22016-10000-26950
Plan Check / Job No.
B22LA17864
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
REMODEL AND TI FOR (E) FULL FLOOR OFFICE TENANT SPACE. WORK INCLUDES MINOR INTERIOR DEMOLITION, INTERIOR PARTITIONS, SUSPEND CEILINGS, AND MILLWORK. NO CHANGE IN EXISTING USE OR OCCUPANCY.
Permit Issued
Issued on 12/20/2022
Issuing Office
Metro
Current Status
Permit Finaled on 2/13/2024

Permit Application Status History

Submitted 9/6/2022 APPLICANT
Assigned to Plan Check Engineer 9/12/2022 LAWRENCE QUIRANTE
Corrections Issued 9/13/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 9/14/2022 APPLICANT
Applicant returned to address corrections 12/15/2022 ZAW HAN
Plan Check Approved 12/20/2022 AUNG SOE
Issued 12/20/2022 APPLICANT
Permit Finaled 2/13/2024 KATY RAMIREZ

Permit Application Clearance Information

Specific Plan Cleared 11/8/2022 MATHEW QUAN
Fire Marshal Fire Life Safety Cleared 12/17/2022 ANDREW KO

Contact Information

Architect Haim,, Jason J; Lic. No.: C27994 149 S BARRIGTON AVENUE #780      LOS ANGELES, CA 90049
Contractor Clune Construction Company L P; Lic. No.: 732107-B 725 SOUTH FIGUEROA STREET   STE 300    LOS ANGELES, CA 90017
Engineer Ekwueme,, Chukwuma Ganiru; Lic. No.: S4416 707 WILSHIRE BLVD STE 4450      LOS ANGELES, CA 90017

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 12/23/2022 Partial Approval JEROME BLACKWOOD
Insulation 12/28/2022 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 1/5/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 1/5/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 1/27/2023 Partial Inspection ALFREDO LOPEZ
Light Gage Steel Frame 2/22/2023 Off-Hour Fees Due
Light Gage Steel Frame 2/23/2023 Not Ready for Inspection RAMAZANALI ALMASI
Structural Steel Frame 2/23/2023 Off-Hour Fees Due
Light Gage Steel Frame 2/24/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 3/1/2023 Partial Inspection KATY RAMIREZ
T-Bar Ceiling 3/1/2023 Partial Inspection KATY RAMIREZ
Drywall Nailing 3/9/2023 Approved KATY RAMIREZ
Drywall Nailing 3/13/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 3/13/2023 Partial Approval KATY RAMIREZ
T-Bar Ceiling 4/6/2023 Approved RAMAZANALI ALMASI
Light Gage Steel Frame 4/26/2023 Partial Approval TIMOTHY POWELL
Drywall Nailing 5/3/2023 Approved DARRYL ARNOLD
Pre-Inspection 5/24/2023 Partial Inspection KATY RAMIREZ
Green Building Rough 6/5/2023 Approved KATY RAMIREZ
Pre-Inspection 6/5/2023 Approved KATY RAMIREZ
Final 6/6/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 6/6/2023 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 6/6/2023 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 6/6/2023 Not Ready for Inspection RAMAZANALI ALMASI
Final 1/17/2024 Not Ready for Inspection KATY RAMIREZ
Green Building Final 1/17/2024 Approved KATY RAMIREZ
Smoke Detectors 1/17/2024 Approved KATY RAMIREZ
Final 2/13/2024 Permit Finaled KATY RAMIREZ