1246 1/2 N EL CENTRO AVE 90038

Certificate Information: 1246 1/2 N EL CENTRO AVE 90038

Application / Permit
22016-10000-26734
Plan Check / Job No.
B22LA17679
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT AND EXISTING 2-CAR GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION. (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d)) . WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
Permit Issued
Issued on 1/24/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 AUNG SOE
Corrections Issued 9/10/2022 AUNG SOE
Building Plans Picked Up 9/15/2022 APPLICANT
Applicant returned to address corrections 9/29/2022 ZAW HAN
Plan Check Approved 12/6/2022 GEORGE ALVAREZ
Issued 1/24/2023 APPLICANT
CofO in Progress 2/23/2026 CRAIG VAUGHAN
Permit Finaled 2/23/2026 DEROLD HAUFF
CofO Issued 2/23/2026 DEROLD HAUFF
Permit Finaled 2/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 9/16/2022 ABEL CASILLAS
Address approval Cleared 11/16/2022 JEANIE LAM
Tenant Habitability Plan Cleared 11/22/2022 MICHAEL SOTO
Eng Process Fee Ord 176,300 Cleared 11/28/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/1/2023 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 12/14/2023 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 1/11/2024 Corrections Issued ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 2/6/2024 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 2/6/2024 Partial Approval ROY SPAULDING
Gas Test 2/6/2024 Corrections Issued ROY SPAULDING
ELECTRICAL-Rough 6/2/2025 Partial Approval CRAIG VAUGHAN
HVAC-Rough 6/2/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 6/2/2025 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 6/27/2025 Partial Inspection BRIAN SULLIVAN
HVAC-Rough 6/27/2025 Partial Inspection BRIAN SULLIVAN
PLUMBING-Rough 6/27/2025 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 7/7/2025 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 7/7/2025 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/7/2025 Corrections Issued CRAIG VAUGHAN
Shower Pan 7/7/2025 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 7/10/2025 Approved BRIAN SULLIVAN
HVAC-Rough 7/10/2025 Approved BRIAN SULLIVAN
PLUMBING-Rough 7/10/2025 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 7/16/2025 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 7/16/2025 Approved CRAIG VAUGHAN
Insulation 7/21/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/21/2025 Partial Approval CRAIG VAUGHAN
Drywall Nailing 7/28/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/28/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 10/15/2025 Approved CRAIG VAUGHAN
ELECTRICAL-Final 10/15/2025 Corrections Issued CRAIG VAUGHAN
Final 10/15/2025 Corrections Issued CRAIG VAUGHAN
HVAC-Final 10/15/2025 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 10/15/2025 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 10/15/2025 Approved CRAIG VAUGHAN
ELECTRICAL-Final 10/21/2025 Approved CRAIG VAUGHAN
HVAC-Final 10/21/2025 Approved CRAIG VAUGHAN
Final 2/13/2026 OK to Issue CofO CRAIG VAUGHAN
Gas Test 2/13/2026 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 2/20/2026 Approved CRAIG VAUGHAN