9657 N HAYVENHURST AVE 91343
Certificate Information: 9657 N HAYVENHURST AVE 91343
- Application / Permit
- 22016-10000-26716
- Plan Check / Job No.
- B22LA17669
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO A.D.U. PER CA Govt. Code 65852.2(e)(1)(A). CONSTRUCTION PER W.F.P.P.
- Permit Issued
- Issued on 9/22/2022
- Issuing Office
- Current Status
- CofO Issued on 6/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/2/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 9/22/2022 | SHANGQIN XIE |
| Issued | 9/22/2022 | APPLICANT |
| CofO in Progress | 6/21/2023 | RAUL OLAGI |
| Permit Finaled | 6/23/2023 | MICHAEL SMITH |
| CofO Issued | 6/23/2023 | MICHAEL SMITH |
| Permit Finaled | 6/23/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/6/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2022 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 9/21/2022 | KIRK LINKLATER |
Contact Information
| Contractor | E & E Builders Inc; Lic. No.: 1060959-B | 22543 VENTURA BLVD STE 214 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/20/2022 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 10/25/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 10/25/2022 | Not Ready for Inspection | RAUL OLAGI |
| Sewer | 10/25/2022 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 11/2/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 11/2/2022 | Approved | RAUL OLAGI |
| Sewer | 11/2/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 12/6/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 12/6/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 12/6/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 12/13/2022 | No Access for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 12/21/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 12/21/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 12/21/2022 | Approved | RAUL OLAGI |
| Insulation | 1/9/2023 | Corrections Issued | RAUL OLAGI |
| Insulation | 1/13/2023 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 1/13/2023 | Corrections Issued | RAUL OLAGI |
| Insulation | 1/20/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 1/20/2023 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/25/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 1/31/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Not Ready | RAUL OLAGI |
| ELECTRICAL-Final | 3/30/2023 | Corrections Issued | RAUL OLAGI |
| Final | 3/30/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 3/30/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 3/30/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 3/30/2023 | Approved | RAUL OLAGI |
| Final | 4/14/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 5/17/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 5/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 6/20/2023 | Approved | RAUL OLAGI |
| Final | 6/20/2023 | OK to Issue CofO | RAUL OLAGI |