6544 W BARTON AVE 90038

Certificate Information: 6544 W BARTON AVE 90038

Application / Permit
22016-10000-26711
Plan Check / Job No.
B22LA17659
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Remodel of existing duplex to include removal of interior wall lath and plaster; remove, replace and new windows and doors; remove and reroof composition roofing; replace plumbing system and fixtures; replace electrical system and fixtures; replace gas system and fixtures; reframe and newly framed interior walls; new HVAC system; new 200 amp dual meter electrical panel; new drywall; new floor, ceiling and wall insulation; replace or new concrete stoops; repair ceiling joist deflection with new support beam and posts.
Permit Issued
Issued on 9/9/2022
Issuing Office
Current Status
Permit Finaled on 4/13/2023

Permit Application Status History

Submitted 9/2/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 JOE VO
Plan Check Approved 9/8/2022 JOE VO
Issued 9/9/2022 APPLICANT
Permit Finaled 4/12/2023 BRIAN SULLIVAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/14/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 9/16/2022 No Access for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 9/16/2022 No Access for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 10/24/2022 Conditional Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 10/24/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 10/24/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 10/24/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/3/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 11/3/2022 Approved JOAQUIN GREENOUGH
Insulation 11/3/2022 Partial Approval JOAQUIN GREENOUGH
Drywall Nailing 11/16/2022 Approved JOAQUIN GREENOUGH
Final 4/5/2023 Partial Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 4/5/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Service/Power Release 4/7/2023 Approved JOAQUIN GREENOUGH
Final 4/12/2023 Permit Finaled BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/12/2023 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 4/12/2023 Approved BRIAN SULLIVAN