912 1/2 S OGDEN DR 90036
Certificate Information: 912 1/2 S OGDEN DR 90036
- Application / Permit
- 22016-10000-26692
- Plan Check / Job No.
- B22LA17643
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 20' X 18' 2-CAR GARAGE TO ADU PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Current Status
- Issued on 12/13/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 9/10/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 10/21/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 10/27/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 11/22/2022 | MOHAMMAD ESMAILI |
| Issued | 12/13/2022 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 9/19/2022 | NOAH MCCOY |
| Address approval | Cleared | 9/20/2022 | WALLIE JONG |
| Sewer availability | Cleared | 9/20/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2022 | WALLIE JONG |
| HPOZ | Cleared | 10/19/2022 | AMANDA KAINER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/6/2023 | Conditional Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 2/14/2023 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/21/2023 | Corrections Issued | MICHAEL LEWIS |
| METHANE-Subgrade | 4/7/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/11/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 5/8/2023 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/15/2023 | Approved | RICHARD DOCKUS |
| Wood Frame | 5/15/2023 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 5/23/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 5/30/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/30/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/6/2023 | Approved | RICHARD DOCKUS |
| Green Building Rough | 6/6/2023 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 6/6/2023 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 6/6/2023 | Approved | RICHARD DOCKUS |
| Insulation | 6/15/2023 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 6/15/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 6/23/2023 | Approved | RICHARD DOCKUS |
| Sewer | 6/23/2023 | Partial Approval | RICHARD DOCKUS |
| Sewer | 7/21/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 7/24/2023 | Approved | SCOTT FINNILA |
| Sewer | 7/24/2023 | Approved | SCOTT FINNILA |
| Final | 5/26/2026 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 5/26/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 5/26/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 5/29/2026 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 5/29/2026 | No Access for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 5/29/2026 | No Access for Inspection | RONNIE MINDANAO |