322 S COMMONWEALTH AVE 90020
Certificate Information: 322 S COMMONWEALTH AVE 90020
- Application / Permit
- 22016-10000-26668
- Plan Check / Job No.
- B22LA17609
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install (2) new Steel Special Cantilever Columns in tuck under parking area.
- Permit Issued
- Issued on 11/21/2023
- Issuing Office
- Current Status
- OK for CofC on 6/4/2024
Permit Application Status History
| Submitted | 9/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | JESSE VIDUYA |
| Corrections Issued | 9/16/2022 | JESSE VIDUYA |
| Quality Review Completed | 9/27/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/2/2023 | JESSE VIDUYA |
| Applicant returned to address corrections | 3/23/2023 | JESSE VIDUYA |
| Applicant returned to address corrections | 4/4/2023 | JESSE VIDUYA |
| Applicant returned to address corrections | 6/21/2023 | JESSE VIDUYA |
| Plan Check Approved | 6/29/2023 | JESSE VIDUYA |
| Issued | 11/21/2023 | APPLICANT |
| OK for CofC | 6/4/2024 | JACOB MYERS |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/17/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Ariel Muller; Lic. No.: 1026822-B | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/4/2023 | Not Ready for Inspection | JACOB MYERS |
| Excavation/Setback/Form/Re-Bar | 1/12/2024 | Partial Approval | JACOB MYERS |
| Wood Frame | 3/7/2024 | Not Ready for Inspection | JACOB MYERS |
| Wood Frame | 3/12/2024 | Partial Approval | JACOB MYERS |
| Deputy Wood Construction | 3/21/2024 | Partial Approval | JACOB MYERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Approved | JACOB MYERS |
| Interior/Exterior Lathing | 4/1/2024 | Approved | JACOB MYERS |
| Final | 5/24/2024 | Not Ready for Inspection | JACOB MYERS |
| METHANE-Final | 5/24/2024 | Not Ready for Inspection | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 5/24/2024 | SGSOV Not Ready | JACOB MYERS |
| Smoke Detectors | 5/24/2024 | Not Ready for Inspection | JACOB MYERS |
| Final | 6/4/2024 | OK for CofC | JACOB MYERS |
| METHANE-Final | 6/4/2024 | Approved | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Approved | JACOB MYERS |
| Smoke Detectors | 6/4/2024 | Approved | JACOB MYERS |