100 N CATALINA ST 90004
Certificate Information: 100 N CATALINA ST 90004
- Application / Permit
- 22016-10000-26655
- Plan Check / Job No.
- B22LA17598
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Add (1) new OMF in tuck under parking area.
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Current Status
- CofC Issued on 12/8/2023
Permit Application Status History
| Submitted | 9/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | BIDYUT RATH |
| Corrections Issued | 9/14/2022 | BIDYUT RATH |
| Quality Review Completed | 9/26/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 2/28/2023 | BIDYUT RATH |
| Applicant returned to address corrections | 3/16/2023 | BIDYUT RATH |
| Plan Check Approved | 3/24/2023 | BIDYUT RATH |
| Issued | 9/26/2023 | APPLICANT |
| OK for CofC | 12/8/2023 | ERNESTO CORRAL |
| OK to Issue CofC | 12/8/2023 | ERNESTO CORRAL |
| CofC Issued | 12/8/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/21/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Ariel Muller; Lic. No.: 1026822-B | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/29/2023 | Partial Inspection | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 10/5/2023 | Conditional Approval | VAHE KELEDJIAN |
| Wood Frame | 10/5/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Wood Frame | 10/11/2023 | Partial Inspection | VAHE KELEDJIAN |
| Wood Frame | 10/17/2023 | No Access for Inspection | VAHE KELEDJIAN |
| Wood Frame | 10/19/2023 | Corrections Issued | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 10/25/2023 | Partial Approval | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Not Ready | JACOB MYERS |
| Smoke Detectors | 11/3/2023 | Approved | JACOB MYERS |
| Final | 12/8/2023 | OK for CofC | ERNESTO CORRAL |
| METHANE-Final | 12/8/2023 | Approved | ERNESTO CORRAL |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Approved | ERNESTO CORRAL |