4623-4625 E MONT EAGLE PL 90041
Certificate Information: 4623-4625 E MONT EAGLE PL 90041
- Application / Permit
- 22016-10000-26542
- Plan Check / Job No.
- B22LA17490
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert attached garage to Accessory Dwelling Unit per GCS 65852.2(e)(1)(A) . Work is per Wood Frame Prescriptive Provisions.
- Permit Issued
- Issued on 2/7/2023
- Issuing Office
- Metro
- Current Status
- Issued on 2/7/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2022 | RICARDO RAMIREZ |
| Corrections Issued | 8/31/2022 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 1/31/2023 | GEORGE ALVAREZ |
| Plan Check Approved | 2/3/2023 | GEORGE ALVAREZ |
| Issued | 2/7/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 1/31/2023 | AMAAN MALIK |
| Grading Pre-Inspection | Cleared | 2/3/2023 | RICARDO RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/22/2025 | Partial Approval | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 1/12/2026 | Conditional Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 1/12/2026 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 1/21/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2026 | Partial Approval | NICHOLAS LOPEZ |
| Green Building Rough | 1/21/2026 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 1/23/2026 | Partial Approval | NICHOLAS LOPEZ |
| Insulation | 1/23/2026 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 2/5/2026 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 2/9/2026 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 2/9/2026 | Approved | NICHOLAS LOPEZ |
| Insulation | 2/10/2026 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 2/18/2026 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 2/23/2026 | Approved | NICHOLAS LOPEZ |
| Final | 4/29/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 4/29/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/29/2026 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 4/29/2026 | Approved | NICHOLAS LOPEZ |
| Sewer | 6/2/2026 | Approved | NICHOLAS LOPEZ |
| Final | 6/5/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 6/5/2026 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/5/2026 | SGSOV Not Ready | NICHOLAS LOPEZ |