4217 S DON CARLOS DR 90008
Certificate Information: 4217 S DON CARLOS DR 90008
- Application / Permit
- 22016-10000-26504
- Plan Check / Job No.
- B22LA17468
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FULL INTERIOR REMODEL AT 1ST AND 2ND FLOORS. CONVERT (E) SOLARIUM AT REAR INTO PART OF THE (N) LIVING ROOM. (N) LAUNDRY ROOM. SEE COMMENTS.
- Permit Issued
- Issued on 3/14/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 9/6/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/7/2022 | KEN GILL |
| Applicant returned to address corrections | 10/25/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 11/16/2022 | SERGIO GUTIERREZ |
| Issued | 3/14/2023 | APPLICANT |
| CofO in Progress | 7/16/2024 | ANTHONY EGSON |
| CofO Issued | 8/5/2024 | DEROLD HAUFF |
| Permit Finaled | 8/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/17/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2022 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 10/19/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Zimmitti Anthony; Lic. No.: 1058893-B | 73 VALLEY STREET PASADENA, CA 91105 |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/29/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/13/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/26/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/26/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 12/14/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/16/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 1/22/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/31/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 1/31/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/31/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/13/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Not Ready for Inspection | JOSE MACIAS |
| Interior/Exterior Lathing | 2/13/2024 | Not Ready for Inspection | JOSE MACIAS |
| BUILDING-Rough-Frame | 2/22/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 2/22/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/26/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 2/26/2024 | Approved | ANTHONY EGSON |
| Structural Steel Frame | 2/26/2024 | Approved | ANTHONY EGSON |
| Insulation | 2/29/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 3/11/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 3/13/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 6/17/2024 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Final | 6/24/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/25/2024 | Approved | ANTHONY EGSON |
| HVAC-Final | 6/25/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 7/2/2024 | Approved | ANTHONY EGSON |
| Final | 7/3/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 7/3/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 7/3/2024 | Approved | ANTHONY EGSON |
| Final | 7/10/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 7/10/2024 | Approved | ANTHONY EGSON |
| Final | 7/15/2024 | OK to Issue CofO | ANTHONY EGSON |