2701 E CESAR E CHAVEZ AVE 90033
Certificate Information: 2701 E CESAR E CHAVEZ AVE 90033
- Application / Permit
- 22016-10000-26488
- Plan Check / Job No.
- B22LA17459
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- MAJOR TENANT IMPROVEMENT TO (E) RESTAURANT (JACK IN THE BOX)
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Current Status
- Permit Finaled on 5/28/2025
Permit Application Status History
| Submitted | 9/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | HERNAN ARREOLA |
| Corrections Issued | 9/27/2022 | LAMAR DAVIS |
| Quality Review Completed | 9/29/2022 | GARO TELMI |
| Applicant returned to address corrections | 6/5/2023 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/15/2023 | HERNAN ARREOLA |
| Plan Check Approved | 3/18/2024 | HERNAN ARREOLA |
| Issued | 4/10/2024 | APPLICANT |
| Permit Finaled | 5/28/2025 | RONALD JIMENEZ |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 1/11/2023 | DAVID URITA |
| Redevelopment Project Area | Cleared | 1/11/2023 | DAVID URITA |
| Food Service Establishment | Cleared | 3/9/2023 | PAWAN VERMA |
| Sewer availability | Cleared | 5/5/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2023 | WALLIE JONG |
| Green Code | Cleared | 12/5/2023 | AARON COSTA |
| DAS Clearance | Cleared | 3/7/2024 | EDDIE GARIN |
| Food establishment approval | Cleared | 3/18/2024 | LACDHS APPROVED |
Contact Information
| Architect | Sargenti,, Robert Jon; Lic. No.: C31054 | 461 FROM ROAD SUITE 255 PARAMUS, NJ 07652 |
| Contractor | R C Pacific Construction Inc; Lic. No.: 721485-B | , |
| Engineer | Sierra,, Jesus Francisco; Lic. No.: S3298 | 2600 CENTERAL AVE STE M UNION CITY, CA 94587 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2024 | Partial Inspection | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 8/7/2024 | Partial Approval | RONALD JIMENEZ |
| Pre-Inspection | 9/9/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 9/9/2024 | Corrections Issued | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 9/23/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Wood Frame | 9/23/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 9/27/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 10/4/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Wood Frame | 10/8/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Interior/Exterior Lathing | 10/17/2024 | Conditional Approval | RONALD JIMENEZ |
| Wood Frame | 10/17/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Insulation | 10/23/2024 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 10/28/2024 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 10/29/2024 | Partial Approval | RONALD JIMENEZ |
| Special/Order Compliance | 10/29/2024 | Corrections Issued | RONALD JIMENEZ |
| Drywall Nailing | 10/31/2024 | Approved | RONALD JIMENEZ |
| Footing/Foundation/Slab | 11/13/2024 | Corrections Issued | RONALD JIMENEZ |
| T-Bar Ceiling | 12/3/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 12/4/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| T-Bar Ceiling | 12/6/2024 | Conditional Approval | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 1/13/2025 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 1/31/2025 | Corrections Issued | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 2/18/2025 | Approved | RONALD JIMENEZ |
| Final | 3/20/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 3/20/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 3/20/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 4/23/2025 | Corrections Issued | RONALD JIMENEZ |
| Green Building Final | 4/23/2025 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 4/23/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 4/23/2025 | Approved | RONALD JIMENEZ |
| Final | 5/28/2025 | Permit Finaled | RONALD JIMENEZ |