3622-3622 1/2 N NORTH BROADWAY 90031
Certificate Information: 3622-3622 1/2 N NORTH BROADWAY 90031
- Application / Permit
- 22016-10000-26462
- Plan Check / Job No.
- B22LA14754
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan - convert (E) 4 car attached garage to ADU per GCS 65852.2(e)(1)(C), no structural work
- Permit Issued
- Issued on 12/19/2023
- Issuing Office
- Current Status
- CofO Issued on 3/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | KELVIN CHUONG |
| Corrections Issued | 8/31/2022 | KELVIN CHUONG |
| Quality Review Completed | 9/6/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 5/15/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 6/9/2023 | KELVIN CHUONG |
| Plan Check Approved | 12/19/2023 | KELVIN CHUONG |
| Issued | 12/19/2023 | APPLICANT |
| CofO in Progress | 2/8/2024 | OSVALDO PARAMO |
| CofO in Progress | 2/8/2024 | OSVALDO PARAMO |
| CofO Issued | 3/11/2024 | DEROLD HAUFF |
| Permit Finaled | 3/11/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 12/28/2022 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 1/3/2023 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 1/3/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 1/3/2023 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2023 | CHRISTOPHER ROCHA |
| "D" conditions | Cleared | 1/17/2023 | SPENCER WEJROWSKI |
| "Q" conditions | Cleared | 1/17/2023 | SPENCER WEJROWSKI |
| CPC | Cleared | 1/17/2023 | SPENCER WEJROWSKI |
| CPC | Cleared | 1/17/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 1/17/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 1/17/2023 | SPENCER WEJROWSKI |
| Hydrant and Access approval | Cleared | 4/7/2023 | LAVEON RIDER |
| DAS Clearance | Cleared | 6/20/2023 | KELVIN CHUONG |
| GPI Written Notices | Cleared | 12/5/2023 | KELVIN CHUONG |
| Grading Pre-Inspection | Cleared | 12/5/2023 | KELVIN CHUONG |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 12/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 12/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/26/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 12/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 12/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 12/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 1/2/2024 | Corrections Issued | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 1/2/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/16/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 1/16/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 1/16/2024 | Partial Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 1/30/2024 | Approved | OSVALDO PARAMO |
| Wood Frame | 1/30/2024 | Approved | OSVALDO PARAMO |
| Insulation | 2/1/2024 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 2/2/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 2/2/2024 | Approved | OSVALDO PARAMO |
| Final | 2/6/2024 | OK to Issue CofO | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 2/6/2024 | Approved | OSVALDO PARAMO |