819 W 105TH ST 90044
Certificate Information: 819 W 105TH ST 90044
- Application / Permit
- 22016-10000-26372
- Plan Check / Job No.
- B22LA17398
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF SFD RELOCATE KITCHEN CONVERT OLD KITCHEN TO 3RD BEDROOM REPLACE (E) KITCHEN DOOR WITH NEW WINDOW ALL WORK DONE PER WFPP ***COMPLY WITH DEPARTMENT ORDER****
- Permit Issued
- Issued on 9/6/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/12/2022
Permit Application Status History
| Submitted | 8/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2022 | KHUONG TRUONG |
| Plan Check Approved | 8/30/2022 | KHUONG TRUONG |
| Issued | 9/6/2022 | APPLICANT |
| Permit Finaled | 12/9/2022 | DANIEL GONZALEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pro Renovation Enterprises Inc; Lic. No.: 989072-B | 11306 E 183RD ST STE 204 CERRITOS, CA 90703 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 9/13/2022 | Approved | KIM DOEPPING |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Partial Approval | KIM DOEPPING |
| HVAC-Rough | 9/27/2022 | Approved | KIM DOEPPING |
| PLUMBING-Rough | 9/27/2022 | Approved | KIM DOEPPING |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | KIM DOEPPING |
| ELECTRICAL-Rough | 9/29/2022 | Approved | KIM DOEPPING |
| Wood Frame | 9/29/2022 | Approved | KIM DOEPPING |
| Insulation | 10/5/2022 | Approved | KIM DOEPPING |
| Insulation | 10/7/2022 | Approved | KIM DOEPPING |
| Drywall Nailing | 10/12/2022 | Approved | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 10/12/2022 | Partial Approval | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 11/4/2022 | Not Ready for Inspection | KIM DOEPPING |
| Interior/Exterior Lathing | 11/8/2022 | Approved | KIM DOEPPING |
| ELECTRICAL-Final | 12/5/2022 | Corrections Issued | DANIEL GONZALEZ |
| Final | 12/5/2022 | Corrections Issued | DANIEL GONZALEZ |
| HVAC-Final | 12/5/2022 | Approved | DANIEL GONZALEZ |
| PLUMBING-Final | 12/5/2022 | Corrections Issued | DANIEL GONZALEZ |
| SGSOV-Seismic Gas S/O Valve | 12/5/2022 | SGSOV Not Ready | DANIEL GONZALEZ |
| Service/Power Release | 12/5/2022 | Approved | DANIEL GONZALEZ |
| Smoke Detectors | 12/5/2022 | Approved | DANIEL GONZALEZ |
| ELECTRICAL-Final | 12/9/2022 | Approved | DANIEL GONZALEZ |
| Final | 12/9/2022 | Permit Finaled | DANIEL GONZALEZ |
| PLUMBING-Final | 12/9/2022 | Approved | DANIEL GONZALEZ |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | DANIEL GONZALEZ |