6309 W 79TH PL 90045
Certificate Information: 6309 W 79TH PL 90045
- Application / Permit
- 22016-10000-26292
- Plan Check / Job No.
- B22LA17368
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN COMPLETE REMODEL - STRUCTURAL ONLY
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Current Status
- Issued on 9/7/2022
Permit Application Status History
| Submitted | 8/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | ZAW HAN |
| Corrections Issued | 9/3/2022 | ZAW HAN |
| Plan Check Approved | 9/7/2022 | ZAW HAN |
| Issued | 9/7/2022 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/7/2022 | MANUEL TEJADA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Tega Builders Inc; Lic. No.: 1041646-B | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/26/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 11/1/2022 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 12/13/2022 | Corrections Issued | HERBERT GIRON |
| Sewer | 12/13/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/15/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 2/15/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 2/15/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/21/2023 | Conditional Approval | HERBERT GIRON |
| Insulation | 2/27/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/20/2023 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Final | 10/18/2023 | Approved | HERBERT GIRON |
| Final | 10/18/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 10/18/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 10/18/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 10/18/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 10/25/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 10/25/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/25/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 10/25/2023 | Approved | JESUS RODRIGUEZ |