4319 W JEFFERSON BLVD 90016
Certificate Information: 4319 W JEFFERSON BLVD 90016
- Application / Permit
- 22016-10000-26287
- Plan Check / Job No.
- B22LA17364
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- T.I. to (E) office building
- Permit Issued
- Issued on 5/3/2023
- Issuing Office
- Current Status
- Permit Finaled on 6/25/2026
Permit Application Status History
| Submitted | 9/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | FERNANDO FLORES |
| Corrections Issued | 9/6/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 1/9/2023 | FERNANDO FLORES |
| Applicant returned to address corrections | 3/24/2023 | SHANGQIN XIE |
| Plan Check Approved | 4/14/2023 | SHANGQIN XIE |
| Issued | 5/3/2023 | APPLICANT |
| Permit Finaled | 11/30/2023 | RICARDO ROBLES |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 2/9/2023 | MAX LODER |
| Community Plan Implem. Overlay | Cleared | 3/9/2023 | KYLE WINSTON |
| Sewer availability | Cleared | 3/24/2023 | JEANIE LAM |
| Redevelopment Project Area | Cleared | 3/28/2023 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2023 | JEANIE LAM |
Contact Information
| Architect | Mahoney,, Eric Foster; Lic. No.: NA31657 | , |
| Contractor | Rindtek Inc; Lic. No.: 966844-B | , |
| Engineer | Haight,, Christopher; Lic. No.: S4596 | 179 TENOR IRVINE, CA 92618 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 6/7/2023 | Partial Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 7/28/2023 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 8/18/2023 | Approved | RAFAEL CORTES |
| Final | 10/11/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 10/11/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 10/11/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 10/25/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 11/16/2023 | Partial Inspection | ALFREDO LOPEZ |
| Green Building Final | 11/16/2023 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 11/16/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 11/30/2023 | Permit Finaled | RICARDO ROBLES |
| Green Building Final | 11/30/2023 | Approved | RICARDO ROBLES |
| Smoke Detectors | 11/30/2023 | Approved | RICARDO ROBLES |