12643-12645 W LAZARD ST 91342

Certificate Information: 12643-12645 W LAZARD ST 91342

Application / Permit
22016-10000-26209
Plan Check / Job No.
B22LA17326
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER STATE LAW . CONSTRUCTION PER W.F.P.P.
Permit Issued
Issued on 9/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 LAWRENCE QUIRANTE
Corrections Issued 9/3/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 9/6/2022 APPLICANT
Plan Check Approved 9/22/2022 GEORGE ALVAREZ
Issued 9/29/2022 APPLICANT
CofO in Progress 3/7/2023 ARAM AVEDISIAN
CofO Issued 3/7/2023 MICHAEL SMITH
Permit Finaled 3/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/7/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/7/2022 MEGAN GODINEZ
Sewer availability Cleared 9/7/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 9/7/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 9/7/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 9/7/2022 MEGAN GODINEZ
Grading Pre-Inspection Cleared 9/20/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/20/2022 Approved ROBERT GOLD
PLUMBING-Rough 11/1/2022 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 11/16/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 11/16/2022 Corrections Issued ARAM AVEDISIAN
Wood Frame 11/16/2022 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 12/14/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 12/14/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/14/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 12/14/2022 Approved ARAM AVEDISIAN
Insulation 12/16/2022 Corrections Issued ARAM AVEDISIAN
Insulation 12/21/2022 Not Ready for Inspection ARAM AVEDISIAN
Drywall Nailing 1/5/2023 Approved ARAM AVEDISIAN
Insulation 1/5/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/5/2023 Partial Approval ARAM AVEDISIAN
Shower Pan 1/5/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 2/6/2023 Approved ARAM AVEDISIAN
Final 2/6/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 2/6/2023 Approved ARAM AVEDISIAN
Green Building Rough 2/6/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 2/6/2023 Approved ARAM AVEDISIAN
Final 3/7/2023 OK to Issue CofO ARAM AVEDISIAN