6311 W 79TH PL 90045

Certificate Information: 6311 W 79TH PL 90045

Application / Permit
22016-10000-25901
Plan Check / Job No.
B22LA17214
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan convert (E) detached garage in to an ADU PER STATE LAW
Permit Issued
Issued on 9/16/2022
Issuing Office
Current Status
CofO Issued on 11/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 KHUONG TRUONG
Corrections Issued 9/2/2022 KHUONG TRUONG
Plan Check Approved 9/16/2022 KHUONG TRUONG
Issued 9/16/2022 APPLICANT
CofO in Progress 10/26/2023 JESUS RODRIGUEZ
Permit Finaled 11/8/2023 DANIEL ORRANTE
CofO Issued 11/8/2023 DANIEL ORRANTE
Permit Finaled 11/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/6/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 9/6/2022 JOSE HERNANDEZ
Sewer availability Cleared 9/6/2022 JOSE HERNANDEZ
Construction near power lines Cleared 9/13/2022 WALTER RAMIREZ
Specific Plan Cleared 9/13/2022 FREDDY GARCIA
Grading Pre-Inspection Cleared 9/16/2022 KHUONG TRUONG

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Tega Builders Inc; Lic. No.: 1041646-B       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/26/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 10/26/2022 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 11/1/2022 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Partial Approval HERBERT GIRON
PLUMBING-Rough 12/13/2022 Corrections Issued HERBERT GIRON
Sewer 12/13/2022 Approved HERBERT GIRON
PLUMBING-Rough 12/15/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Conditional Approval HERBERT GIRON
Interior/Exterior Lathing 1/26/2023 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 1/27/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 2/15/2023 Conditional Approval HERBERT GIRON
Green Building Rough 2/15/2023 Approved HERBERT GIRON
HVAC-Rough 2/15/2023 Approved HERBERT GIRON
Insulation 2/28/2023 Approved HERBERT GIRON
Drywall Nailing 3/20/2023 Approved HERBERT GIRON
Shower Pan 4/12/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 4/17/2023 Approved RICHARD STEINBACH
PLUMBING-Final 9/6/2023 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 10/18/2023 Corrections Issued HERBERT GIRON
Final 10/18/2023 Corrections Issued HERBERT GIRON
Green Building Final 10/18/2023 Approved HERBERT GIRON
HVAC-Final 10/18/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 10/18/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 10/18/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/25/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/25/2023 Approved JESUS RODRIGUEZ
Final 10/25/2023 OK to Issue CofO JESUS RODRIGUEZ
Gas Test 10/25/2023 Approved JESUS RODRIGUEZ
HVAC-Final 10/25/2023 Approved JESUS RODRIGUEZ