3925 S DUBLIN AVE 90008

Certificate Information: 3925 S DUBLIN AVE 90008

Application / Permit
22016-10000-25809
Plan Check / Job No.
B22LA17149
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF (E) SFD INCLUDING RECONFIGURING FLOOR PLAN AND REPLACING DOORS AND WINDOWS AND REMOVING (E) PORTE COCHERE . ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/7/2023
Issuing Office
Current Status
Permit Finaled on 6/3/2024

Permit Application Status History

Submitted 9/13/2022 APPLICANT
Assigned to Plan Check Engineer 9/19/2022 OMAR GARNICA
Corrections Issued 9/20/2022 OMAR GARNICA
Applicant returned to address corrections 10/7/2022 SARKIS HARABEDIAN
Plan Check Approved 10/11/2022 OMAR GARNICA
Issued 6/7/2023 APPLICANT
Permit Finaled 5/31/2024 ANTHONY EGSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Valencia Construction Company; Lic. No.: 1015167-B       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/12/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 7/18/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 8/22/2023 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 8/22/2023 Corrections Issued BRENDAN MORELLI
HVAC-Rough 8/22/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 8/22/2023 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 8/25/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 8/25/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/25/2023 Partial Approval STUART CHAPMAN
PLUMBING-Rough 8/25/2023 Approved STUART CHAPMAN
Deputy Wood Construction 8/30/2023 Approved ANTHONY EGSON
Insulation 8/31/2023 Approved ANTHONY EGSON
Insulation 9/5/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved ANTHONY EGSON
Special/Order Compliance 10/3/2023 Approved ANTHONY EGSON
Drywall Nailing 12/19/2023 Approved ANTHONY EGSON
Shower Pan 12/19/2023 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 12/22/2023 Approved JOSH MEISTER
Shower Pan 12/22/2023 Approved JOSH MEISTER
ELECTRICAL-Final 5/9/2024 Corrections Issued ANTHONY EGSON
Final 5/9/2024 Not Ready for Inspection ANTHONY EGSON
Gas Test 5/9/2024 Approved ANTHONY EGSON
HVAC-Final 5/9/2024 Approved ANTHONY EGSON
PLUMBING-Final 5/9/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Approved ANTHONY EGSON
Service/Power Release 5/9/2024 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 5/9/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 5/14/2024 Not Ready for Inspection ANTHONY EGSON
Final 5/14/2024 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 5/14/2024 Approved ANTHONY EGSON
Smoke Detectors 5/14/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 5/24/2024 Not Ready for Inspection ANTHONY EGSON
Final 5/24/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 5/31/2024 Approved ANTHONY EGSON
Final 5/31/2024 Permit Finaled ANTHONY EGSON