6725 W SUNSET BLVD #110 90028
Certificate Information: 6725 W SUNSET BLVD #110 90028
- Application / Permit
- 22016-10000-25750
- Plan Check / Job No.
- B22LA17119
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT TO (E) STUDIO AND OFFICE. T.I. TO EXISTING TENANT SPACE. NEW PARTITION WALLS, CEILING, LIGHTING, POWER, AND FINISHES. DEMISING WALL TO SEPARATE TENANT SPACE (WORK AT 1ST FLOOR, AREA OF WORK: 3,000 SF)
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/6/2023
Permit Application Status History
| Submitted | 8/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | GEORGE ALVAREZ |
| Corrections Issued | 10/17/2022 | FERNANDO FLORES |
| Plan Check Approved | 11/9/2022 | SAMUEL GONZALEZ |
| Issued | 11/18/2022 | APPLICANT |
| Permit Finaled | 4/6/2023 | RONALD JIMENEZ |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 10/19/2022 | MAX LODER |
| ZA Case | Cleared | 10/25/2022 | OMAR GALICIA |
| "D" conditions | Cleared | 10/31/2022 | RYAN LY |
| Redevelopment Project Area | Cleared | 11/1/2022 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 11/9/2022 | ABEL CASILLAS |
Contact Information
| Architect | Algaze,, Nelson; Lic. No.: C21090 | 1524 1ST STREET MANHATTAN BEACH, CA 90266 |
| Contractor | Cannon Constructors South Inc; Lic. No.: 900698-B | 17000 VENTURA BLVD #301 ENCINO, CA 91316 |
| Engineer | Schulz,, Les Eric; Lic. No.: S2570 | 346 N LIMA SIERRA MADRE, CA 91024 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 11/22/2022 | Partial Approval | TED RIES |
| Wood Frame | 11/22/2022 | Partial Approval | TED RIES |
| Light Gage Steel Frame | 12/12/2022 | Approved | JONATHAN QUACH |
| Drywall Nailing | 12/14/2022 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 1/17/2023 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 1/20/2023 | Approved | EDWIN GREGORYONA |
| T-Bar Ceiling | 1/24/2023 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Not Required | ALFREDO LOPEZ |
| Final | 4/5/2023 | Partial Inspection | RONALD JIMENEZ |
| Final | 4/6/2023 | Permit Finaled | RONALD JIMENEZ |
| Green Building Final | 4/6/2023 | Approved | RONALD JIMENEZ |
| Smoke Detectors | 4/6/2023 | Approved | RONALD JIMENEZ |