101 S THE GROVE DR 150c 90036
Certificate Information: 101 S THE GROVE DR 150c 90036
- Application / Permit
- 22016-10000-25649
- Plan Check / Job No.
- B22LA17011
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT - NON-STRUCTURAL REMODEL TO (E) OFFICE. NO CHANGE OF USE/PARKING.
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Current Status
- Issued on 12/13/2022
Permit Application Status History
| Submitted | 8/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 8/31/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 11/3/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 11/16/2022 | MOHAMMAD ESMAILI |
| Issued | 12/13/2022 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/23/2022 | RUBEN VASQUEZ |
| "T" removal | Cleared | 9/23/2022 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 9/23/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/23/2022 | RUBEN VASQUEZ |
Contact Information
| Architect | Wilder,, Arthur J; Lic. No.: NA27915 | , |
| Contractor | C T West Construction Inc; Lic. No.: 974403-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Methane Barrier | 1/12/2023 | Approved | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 1/12/2023 | Approved | ALFREDO LOPEZ |
| Light Gage Steel Frame | 1/20/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 1/23/2023 | Approved | ALFREDO LOPEZ |
| Final | 2/2/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 2/2/2023 | Corrections Issued | DARRYL ARNOLD |
| Special/Order Compliance | 2/3/2023 | Partial Approval | JEROME BLACKWOOD |