3923 S BUDLONG AVE 90037
Certificate Information: 3923 S BUDLONG AVE 90037
- Application / Permit
- 22016-10000-25634
- Plan Check / Job No.
- B22LA16999
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) Detached Garage into an ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/29/2022
- Issuing Office
- Current Status
- CofO Issued on 1/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2022 | SHANGQIN XIE |
| Corrections Issued | 9/1/2022 | SHANGQIN XIE |
| Plan Check Approved | 11/26/2022 | SHANGQIN XIE |
| Issued | 11/29/2022 | APPLICANT |
| CofO in Progress | 1/11/2024 | SABAS ALONSO |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
| CofO Issued | 1/13/2024 | DEROLD HAUFF |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/6/2022 | KENTON TRINH |
| ZI | Cleared | 9/6/2022 | KENTON TRINH |
| Address approval | Cleared | 9/8/2022 | WALLIE JONG |
| Sewer availability | Cleared | 9/8/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2022 | WALLIE JONG |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2023 | Corrections Issued | SABAS ALONSO |
| Sewer | 5/2/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/2/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/16/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/24/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 5/24/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 5/24/2023 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/21/2023 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 6/21/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 6/21/2023 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/27/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 6/27/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 6/27/2023 | Approved | SABAS ALONSO |
| Insulation | 7/3/2023 | Conditional Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/3/2023 | Approved | MICHAEL LEWIS |
| Insulation | 7/10/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 7/18/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 10/24/2023 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 10/24/2023 | Partial Approval | SABAS ALONSO |
| Final | 12/11/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/11/2023 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 12/11/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/14/2023 | Approved | SABAS ALONSO |
| Shower Pan | 12/14/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 1/2/2024 | Approved | SABAS ALONSO |
| Final | 1/2/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 1/2/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 1/2/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/2/2024 | SGSOV Approved | SABAS ALONSO |
| Final | 1/5/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 1/10/2024 | Approved | SABAS ALONSO |
| Final | 1/10/2024 | OK to Issue CofO | SABAS ALONSO |
| HVAC-Final | 1/10/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 1/10/2024 | Approved | SABAS ALONSO |