6922 W 84TH PL 90045
Certificate Information: 6922 W 84TH PL 90045
- Application / Permit
- 22016-10000-25631
- Plan Check / Job No.
- B22LA16995
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 20' X 20' DETACHED GARAGE TO AN ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Current Status
- CofO Issued on 1/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2022 | OMAR GARNICA |
| Corrections Issued | 8/28/2022 | OMAR GARNICA |
| Applicant returned to address corrections | 11/9/2022 | OMAR GARNICA |
| Plan Check Approved | 3/3/2023 | OMAR GARNICA |
| Issued | 6/13/2023 | APPLICANT |
| CofO in Progress | 1/9/2024 | BOBBY KEY |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
| CofO Issued | 1/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 9/22/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 2/11/2023 | RIDWAN HARDY |
Contact Information
| Contractor | A P Remodeling Inc; Lic. No.: 1049032-B | , |
| Contractor | Ap Remodeling Inc; Lic. No.: 1049032-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/28/2023 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 8/1/2023 | Corrections Issued | BOBBY KEY |
| Drywall Nailing | 8/1/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 8/1/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 8/1/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/1/2023 | Approved | BOBBY KEY |
| Deputy Drilled-In Anchors | 8/2/2023 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 8/8/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 8/8/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 8/8/2023 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 8/8/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 10/3/2023 | Not Ready for Inspection | RICHARD STEINBACH |
| HVAC-Rough | 10/3/2023 | Approved | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 10/3/2023 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 10/5/2023 | Conditional Approval | HERBERT GIRON |
| Green Building Rough | 10/5/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 10/5/2023 | Partial Approval | HERBERT GIRON |
| Verify Sprinkler Sign Off | 10/5/2023 | Approved | HERBERT GIRON |
| Insulation | 10/10/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/13/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 10/13/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/13/2023 | Approved | BOBBY KEY |
| Shower Pan | 10/13/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 11/22/2023 | Corrections Issued | BOBBY KEY |
| Final | 11/22/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 11/22/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 11/22/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 11/22/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/3/2024 | Corrections Issued | BOBBY KEY |
| Final | 1/3/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 1/3/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 1/3/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Not Ready | BOBBY KEY |
| ELECTRICAL-Final | 1/8/2024 | Approved | BOBBY KEY |
| Final | 1/8/2024 | OK to Issue CofO | BOBBY KEY |
| PLUMBING-Final | 1/8/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/8/2024 | SGSOV Approved | BOBBY KEY |