2958 N TYBURN ST 90039

Certificate Information: 2958 N TYBURN ST 90039

Application / Permit
22016-10000-25505
Plan Check / Job No.
B22LA16910
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan KITCHEN AND MASTER BATH ROOM INTERIOR REMODEL
Permit Issued
Issued on 9/8/2022
Issuing Office
Current Status
Issued on 9/8/2022

Permit Application Status History

Submitted 8/23/2022 APPLICANT
Assigned to Plan Check Engineer 8/29/2022 ZAW HAN
Corrections Issued 8/30/2022 ZAW HAN
Plan Check Approved 9/8/2022 ZAW HAN
Issued 9/8/2022 APPLICANT

Permit Application Clearance Information

ZI Cleared 9/2/2022 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 9/6/2022 JEANETTE VONG
Sewer availability Cleared 9/6/2022 JEANETTE VONG

Contact Information

Contractor Build Method Construction Inc; Lic. No.: 1059684-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/23/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/11/2022 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/11/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/11/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 10/11/2022 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 10/11/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 10/11/2022 Corrections Issued HAMIK HARTOUNIAN
Shower Pan 10/13/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/17/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 10/17/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/18/2022 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 10/18/2022 Approved HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 10/19/2022 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 10/19/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/24/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 10/24/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/24/2022 Partial Approval HAMIK HARTOUNIAN
MERV13>=Rough 10/24/2022 Approved HAMIK HARTOUNIAN
Insulation 10/25/2022 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/31/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 10/31/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Drywall Nailing 11/3/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 11/8/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 12/9/2022 Corrections Issued KATHRYN BUTTERWORTH
Final 12/9/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Final 12/9/2022 Approved KATHRYN BUTTERWORTH
MERV13>=Final 12/9/2022 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 12/9/2022 Approved KATHRYN BUTTERWORTH
Smoke Detectors 12/9/2022 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 12/15/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Final 12/15/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 12/15/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Final 12/15/2022 Approved HAMIK HARTOUNIAN