2631 S MANHATTAN PL 90018

Certificate Information: 2631 S MANHATTAN PL 90018

Application / Permit
22016-10000-25477
Plan Check / Job No.
B22LA16897
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
eplan INTERIOR REMODEL TO (E) APARTMENT TO CREATE AN ADDITIONAL BEDROOM IN EVERY UNIT
Permit Issued
Issued on 1/18/2023
Issuing Office
Current Status
Issued on 1/18/2023

Permit Application Status History

Submitted 8/24/2022 APPLICANT
Assigned to Plan Check Engineer 8/30/2022 FERNANDO FLORES
Corrections Issued 8/31/2022 FERNANDO FLORES
Plan Check Approved 12/31/2022 FERNANDO FLORES
Issued 1/18/2023 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 12/6/2022 ISMAEL HERNANDEZ
HPOZ Cleared 12/13/2022 DANIEL MATA

Contact Information

Contractor Simcity Construction Inc; Lic. No.: 1027407-B       ,
Contractor Simcity Construction, Inc.; Lic. No.: 1027407-B       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/20/2023 Conditional Approval MARTIN TAVITIAN
Footing/Foundation/Slab 1/20/2023 Approved MARTIN TAVITIAN
Wood Frame 5/30/2023 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 7/5/2023 Partial Approval MARTIN TAVITIAN
Insulation 7/7/2023 Approved MARTIN TAVITIAN
Drywall Nailing 7/10/2023 Approved MARTIN TAVITIAN
Interior/Exterior Lathing 7/10/2023 Approved MARTIN TAVITIAN