ePlan PROPOSED MAJOR REMODEL TO EXISTING SINGLE FAMILY DWELLING, CONVERTING EXISTING 3 BEDROOM 3 BATH INTO 5 BEDROOMS 4 BATHS, CREATING A ROOF DECK, CONVERTING A PORTION OF EXISTING COVERED PATIO INTO HABITABLE AREA. ***REQUIRED TO BE SPRINKLERED PER NFPA 13 D***
Permit Issued
Issued on 8/29/2023
Issuing Office
Current Status
Permit Finaled on 12/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2022 APPLICANT
Assigned to Plan Check Engineer 8/30/2022 MICHAEL LOPEZ
Corrections Issued 9/12/2022 MICHAEL LOPEZ
Quality Review Completed 9/19/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 3/8/2023 MICHAEL LOPEZ
Applicant returned to address corrections 6/8/2023 MICHAEL LOPEZ
Applicant returned to address corrections 6/29/2023 MICHAEL LOPEZ
Plan Check Approved 8/18/2023 MICHAEL LOPEZ
No Progress 8/29/2023 MICHAEL LOPEZ
Plan Check Approved 8/29/2023 MICHAEL LOPEZ
Issued 8/29/2023 APPLICANT
Permit Finaled 12/3/2025 JACK KARGODORIAN

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/17/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/5/2023 CARLOS AGUILERA
Sewer availability Cleared 7/5/2023 CARLOS AGUILERA

Contact Information

Contractor Adr Pro Builders Inc; Lic. No.: 1096284-B       ,
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/14/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 9/14/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/15/2023 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 9/19/2023 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 10/10/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 10/10/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 10/17/2023 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 10/18/2023 Conditional Approval JUAN VALENZUELA
Underground Mechanical 11/14/2023 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 3/4/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 5/10/2024 Partial Approval THOMAS FINNILA
Deputy Wood Construction 5/10/2024 Conditional Approval THOMAS FINNILA
Green Building Rough 5/10/2024 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 5/10/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval JACK KARGODORIAN
Green Building Rough 6/11/2024 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Rough 6/11/2024 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Partial Approval JACK KARGODORIAN
Green Building Rough 6/17/2024 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Rough 6/17/2024 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 8/9/2024 Approved JACK KARGODORIAN
HVAC-Rough 8/9/2024 Corrections Issued JACK KARGODORIAN
HVAC-Rough 8/22/2024 No Access for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 8/22/2024 No Access for Inspection JACK KARGODORIAN
PLUMBING-Rough 8/22/2024 No Access for Inspection JACK KARGODORIAN
HVAC-Rough 8/28/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 8/28/2024 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 8/28/2024 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 8/29/2024 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 9/5/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 9/5/2024 Not Ready for Inspection SALVADOR MARTINEZ
MERV13>=Rough 9/5/2024 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 9/5/2024 Corrections Issued SALVADOR MARTINEZ
Insulation 11/19/2024 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 12/4/2024 Approved JACK KARGODORIAN
Green Building Rough 12/4/2024 Approved JACK KARGODORIAN
Insulation 12/4/2024 Approved JACK KARGODORIAN
MERV13>=Rough 12/4/2024 Approved JACK KARGODORIAN
Drywall Nailing 12/19/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 1/3/2025 Approved JACK KARGODORIAN
HVAC-Rough 1/15/2025 Partial Inspection MISAEL ESPARZA
Insulation 1/15/2025 Partial Inspection MISAEL ESPARZA
Interior/Exterior Lathing 1/15/2025 Approved MISAEL ESPARZA
Final 8/14/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 8/14/2025 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Final 8/14/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 8/14/2025 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 8/14/2025 Approved JACK KARGODORIAN
Final 9/10/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 9/10/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/10/2025 SGSOV Approved JACK KARGODORIAN
Final 12/3/2025 Permit Finaled JACK KARGODORIAN