1300 W EXPOSITION BLVD 90018

Certificate Information: 1300 W EXPOSITION BLVD 90018

Application / Permit
22016-10000-25263
Plan Check / Job No.
B22LA16744
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePlan Change of use from Service Station to Office Demolition of existing storage space at the back. Interior/exterior alteration "COMPLY WITH DEPARTMENT ORDER effective date 11/16/2016. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 10/10/2022
Issuing Office
Current Status
CofO Issued on 4/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 8/29/2022 LUKE GONZALES
Corrections Issued 8/30/2022 LUKE GONZALES
Applicant returned to address corrections 9/29/2022 SHANGQIN XIE
Plan Check Approved 10/6/2022 ADAM HEGAZI
Issued 10/10/2022 APPLICANT
CofO in Progress 4/21/2023 ERNESTO CORRAL
Permit Finaled 4/21/2023 ERNESTO CORRAL
CofO Issued 4/21/2023 ERNESTO CORRAL
Permit Finaled 4/21/2023 ERNESTO CORRAL

Permit Application Clearance Information

ZA Case Cleared 9/9/2022 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 9/13/2022 ADRIAN SANCHEZ
Sewer availability Cleared 9/13/2022 ADRIAN SANCHEZ
Comm Cor/Mini-Mall Cleared 9/22/2022 MAXFIELD VERMY
"D" conditions Cleared 9/28/2022 RAFAEL FONTES
Community Plan Implem. Overlay Cleared 9/28/2022 RAFAEL FONTES

Contact Information

Architect Afshari,, Ashkan; Lic. No.: C34486 6151 CANTERBURY DRIVE   #302    CULVER CITY, CA
Contractor Parsa Design & Development Inc; Lic. No.: 1047027-B       ,
Engineer Tajvidi,, Seyed Mohammad; Lic. No.: C84559 9163 LEROY STREET      SAN GABRIEL, CA 91775

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/21/2022 Approved RUSSELL BONVOULOIR
Light Gage Steel Frame 12/14/2022 Partial Inspection ALAN MORELOS
Insulation 12/21/2022 Not Ready for Inspection ALAN MORELOS
Wood Frame 12/21/2022 Not Ready for Inspection ALAN MORELOS
Light Gage Steel Frame 1/12/2023 Approved MARTIN TAVITIAN
Drywall Nailing 1/18/2023 Approved MARTIN TAVITIAN
Light Gage Steel Frame 1/18/2023 Approved MARTIN TAVITIAN
Drywall Nailing 1/26/2023 Approved MARTIN TAVITIAN
Wood Frame 1/26/2023 Approved MARTIN TAVITIAN
Final 2/8/2023 Not Ready for Inspection MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV No Gas MARTIN TAVITIAN
Smoke Detectors 2/8/2023 Not Ready for Inspection MARTIN TAVITIAN
T-Bar Ceiling 2/9/2023 Not Ready for Inspection ALAN MORELOS
T-Bar Ceiling 2/10/2023 Approved MARTIN TAVITIAN
Pre-Inspection 2/13/2023 Approved MARTIN TAVITIAN
Final 3/17/2023 Partial Approval MARTIN TAVITIAN
Smoke Detectors 3/17/2023 Approved MARTIN TAVITIAN