12100 W OLYMPIC BLVD Level 3 90064
Certificate Information: 12100 W OLYMPIC BLVD Level 3 90064
- Application / Permit
- 22016-10000-25261
- Plan Check / Job No.
- B22LA16742
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePlan TENANT IMPROVEMENT TO (E) OFFICE. NEW RESTROOMS, BREAK ROOM, CONFERENCE ROOMS - Level 3
- Permit Issued
- Issued on 11/14/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/3/2023
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | LAMAR DAVIS |
| Corrections Issued | 9/13/2022 | LAMAR DAVIS |
| Quality Review Completed | 9/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 11/3/2022 | LAMAR DAVIS |
| Issued | 11/14/2022 | APPLICANT |
| Permit Finaled | 10/3/2023 | FARHAD DADBIN |
Permit Application Clearance Information
| Green Code | Cleared | 9/13/2022 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 10/17/2022 | Hernan Arreola |
Contact Information
| Architect | Blank,, Joel; Lic. No.: C25176 | 2129 HOLMBY AVE LOS ANGELES, CA 90025 |
| Architect | Blank,, Joel; Lic. No.: NA25176 | , |
| Contractor | Clune Construction Company L P; Lic. No.: 732107-B | 725 SOUTH FIGUEROA STREET STE 300 LOS ANGELES, CA 90017 |
| Engineer | Lee,, James; Lic. No.: S6493 | 950 SOUTH GRAND AVENUE, SUITE 400 LOS ANGELES, CA 90015 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/13/2022 | Approved | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 12/13/2022 | Approved | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 1/20/2023 | No Access for Inspection | MICHAEL PETRUSKO |
| Excavation/Setback/Form/Re-Bar | 2/1/2023 | Approved | AMANUEL BERHE |
| Excavation/Setback/Form/Re-Bar | 2/15/2023 | Partial Approval | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 2/15/2023 | Partial Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 2/17/2023 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 2/22/2023 | Partial Approval | SORIN CIRSTOIU |
| Insulation | 2/22/2023 | Approved | SORIN CIRSTOIU |
| Light Gage Steel Frame | 3/3/2023 | Partial Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 3/21/2023 | Approved | AMANUEL BERHE |
| Drywall Nailing | 3/22/2023 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Light Gage Steel Frame | 5/4/2023 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 5/8/2023 | Partial Approval | ALAN NOVAK |
| Drywall Nailing | 5/24/2023 | Partial Approval | ALAN NOVAK |
| T-Bar Ceiling | 5/25/2023 | Approved | MICHAEL PETRUSKO |
| Pre-Inspection | 6/13/2023 | Approved | PAUL DAVIDSON |
| Final | 7/10/2023 | Conditional Approval | FARHAD DADBIN |
| Green Building Final | 7/10/2023 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 7/10/2023 | Approved | FARHAD DADBIN |
| Final | 10/3/2023 | Permit Finaled | FARHAD DADBIN |