8413 N TYRONE AVE 91402

Certificate Information: 8413 N TYRONE AVE 91402

Application / Permit
22016-10000-25124
Plan Check / Job No.
B22LA16710
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION TO ADU PER STATE LAW
Permit Issued
Issued on 12/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2022 APPLICANT
Assigned to Plan Check Engineer 8/22/2022 KHUONG TRUONG
Corrections Issued 8/23/2022 KHUONG TRUONG
Building Plans Picked Up 9/30/2022 APPLICANT
Issued 12/28/2022 APPLICANT
CofO in Progress 6/23/2023 GREGG CUMMINGS
Permit Finaled 7/21/2023 DANIEL ORRANTE
CofO Issued 7/21/2023 DANIEL ORRANTE
Permit Finaled 7/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/7/2022 ROMAN GUTIERREZ
Sewer availability Cleared 10/7/2022 ROMAN GUTIERREZ
Construction near power lines Cleared 12/3/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 12/23/2022 ROMAN GUTIERREZ

Contact Information

Contractor Jll General Construction; Lic. No.: 1079081-B 2743 WASHINGTON AVE      EL MONTE, CA 91733
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 1/24/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 1/24/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 1/30/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 2/1/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 2/1/2023 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 2/6/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 2/6/2023 Approved GREGG CUMMINGS
PLUMBING-Rough 2/6/2023 Partial Approval GREGG CUMMINGS
Sewer 2/6/2023 Approved GREGG CUMMINGS
Deputy Drilled-In Anchors 3/8/2023 Conditional Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/9/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 3/9/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/9/2023 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/16/2023 No Access for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/16/2023 No Access for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 3/16/2023 No Access for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/17/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 3/17/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 3/17/2023 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/17/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/21/2023 Approved JENNIFER RABUCHIN
Green Building Rough 3/21/2023 Partial Approval JENNIFER RABUCHIN
Insulation 3/22/2023 Approved MATTHEW NELSON
Drywall Nailing 4/11/2023 Approved GREGG CUMMINGS
Green Building Rough 4/11/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 4/11/2023 Partial Approval GREGG CUMMINGS
Underground Mechanical 5/5/2023 Partial Approval GREGG CUMMINGS
Final 5/26/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 5/26/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 5/26/2023 Approved GREGG CUMMINGS
Final 6/3/2023 Off-Hour Fees Due
Final 6/8/2023 Corrections Issued DAVID MATSON
ELECTRICAL-Final 6/22/2023 Approved GREGG CUMMINGS
Final 6/22/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 6/22/2023 Approved GREGG CUMMINGS
PLUMBING-Final 6/22/2023 Approved GREGG CUMMINGS