601 W 5TH ST Suite 800 90731
Certificate Information: 601 W 5TH ST Suite 800 90731
- Application / Permit
- 22016-10000-25023
- Plan Check / Job No.
- B22LA16642
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT TO (E) OFFICE SPACE
- Permit Issued
- Issued on 2/1/2023
- Issuing Office
- Current Status
- Permit Finaled on 6/21/2023
Permit Application Status History
| Submitted | 8/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 9/2/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 1/24/2023 | JEROME MAGAT PALMA |
| Issued | 2/1/2023 | APPLICANT |
| Permit Finaled | 6/20/2023 | KATY RAMIREZ |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 1/13/2023 | SARAH ZHANG |
Contact Information
| Architect | Fridlund,, David John; Lic. No.: C20787 | 1917 SILVER WOOD LANE LOS ANGELES, CA 90041 |
| Contractor | Howard Building Corporation; Lic. No.: 445804-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Structural Steel Frame | 3/6/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Light Gage Steel Frame | 3/14/2023 | Partial Approval | RAMAZANALI ALMASI |
| Insulation | 3/15/2023 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 3/17/2023 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 3/29/2023 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 3/30/2023 | Partial Approval | KATY RAMIREZ |
| Insulation | 3/30/2023 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 4/7/2023 | Approved | VAHE KELEDJIAN |
| T-Bar Ceiling | 4/7/2023 | Approved | NICK DANERI |
| Final | 5/30/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Final | 5/30/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 5/30/2023 | SGSOV Not Ready | JEROME BLACKWOOD |
| Smoke Detectors | 5/30/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 6/12/2023 | Corrections Issued | KATY RAMIREZ |
| Green Building Final | 6/12/2023 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 6/12/2023 | Approved | KATY RAMIREZ |
| Final | 6/15/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 6/20/2023 | Permit Finaled | KATY RAMIREZ |