307 E 118TH ST 90061

Certificate Information: 307 E 118TH ST 90061

Application / Permit
22016-10000-25009
Plan Check / Job No.
B22LA16633
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT THE (E) 18'-0" X 12'-0" DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). - ALL WORK PER WFPP
Permit Issued
Issued on 12/19/2022
Issuing Office
Current Status
CofO Issued on 11/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2022 APPLICANT
Assigned to Plan Check Engineer 8/22/2022 LUISANGEL VALENZUELA
Corrections Issued 8/23/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/13/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/26/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 12/14/2022 DANIEL ABRAMYAN
Plan Check Approved 12/16/2022 GEORGE ALVAREZ
Issued 12/19/2022 APPLICANT
CofO in Progress 11/21/2023 JOHN KLARIN
Permit Finaled 11/21/2023 ANSON MAGLASANG
CofO Issued 11/21/2023 ANSON MAGLASANG
Permit Finaled 11/21/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/6/2022 JEANETTE VONG
Sewer availability Cleared 9/6/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/13/2022 JEANETTE VONG

Contact Information

Contractor Golden State One Construction Corporation; Lic. No.: 975468-B       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/3/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/4/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 8/4/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Approved JOHN KLARIN
HVAC-Rough 8/4/2023 Approved JOHN KLARIN
MERV13>=Rough 8/4/2023 Approved JOHN KLARIN
PLUMBING-Rough 8/4/2023 Approved JOHN KLARIN
Sewer 8/4/2023 Partial Approval JOHN KLARIN
Insulation 8/28/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 8/28/2023 Approved JOHN KLARIN
Shower Pan 8/28/2023 Approved JOHN KLARIN
Underground Mechanical 8/28/2023 Corrections Issued JOHN KLARIN
Drywall Nailing 9/8/2023 Approved JOHN KLARIN
Final 11/8/2023 Corrections Issued JOHN KLARIN
MERV13>=Final 11/8/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Not Ready JOHN KLARIN
Smoke Detectors 11/8/2023 Approved JOHN KLARIN
Final 11/13/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Not Ready JOHN KLARIN
Final 11/17/2023 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Not Ready JOHN KLARIN
Final 11/21/2023 OK to Issue CofO JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Approved JOHN KLARIN