4701 W ADAMS BLVD 90016

Certificate Information: 4701 W ADAMS BLVD 90016

Application / Permit
22016-10000-24817
Plan Check / Job No.
B22LA16457
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(11) Hotel
Work Description
NFPA 13R FIRE SPRINKLERS REQUIRED. PROJECT HOMEKEY: MULTIFAMILY HOUSING PROGRAM PER GCS 50675.1.3. CHANGE OF USE FROM (E) NON-TRANSIENT HOTEL (R-2) TO MULTIFAMILY HOUSING, 100% AFFORDABLE, WITHIN (E) 2-STORY TYPE VB BUILDING. CONVERT PARKING GARAGE TO SUPPORTIVE OFFICE.
Permit Issued
Issued on 5/13/2024
Issuing Office
Current Status
Issued on 5/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/18/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 KEVIN MORALES
Corrections Issued 8/29/2022 KEVIN MORALES
Quality Review Completed 9/1/2022 EUGENE BARBEAU
Applicant returned to address corrections 10/27/2022 KEVIN MORALES
Plan Check Approved 10/19/2023 KEVIN MORALES
Issued 5/13/2024 APPLICANT
TCO Issued (Expire Date: 09-22-2026) 3/26/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 9/3/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/6/2022 JEANETTE VONG
Community Plan Implem. Overlay Cleared 9/22/2022 EILEEN HUNT
Community Plan Implem. Overlay Cleared 10/4/2022 KYLE WINSTON
Historic Resource Verification Cleared 10/7/2022 MAX LODER
Redevelopment Project Area Cleared 11/15/2022 GRACIELA ACOSTA
Green Code Cleared 11/23/2022 AARON COSTA
SB8 RUD Cleared 12/19/2022 JESSICA WANG
Fire Marshal Fire Life Safety Cleared 1/12/2023 WILLIAM JOHNS
Miscellaneous Cleared 4/13/2023 MARITZA PRZEKOP
Permanent Supportive Housing Cleared 4/13/2023 MARITZA PRZEKOP
Low Impact Development Cleared 6/19/2023 MARTIN FRAGOSO
Public Housing Cleared 9/21/2023 GUS VINDELL
DAS Clearance Cleared 10/16/2023 Rodolfo Arias

Contact Information

Contractor Level Construction Group Inc; Lic. No.: 991265-B       ,
Engineer Naraghi-Arani,, Kamran; Lic. No.: C40985 30423 CANWOOD ST STE 223      AGOURA HILLS, CA 91301

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/3/2024 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 7/3/2024 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 7/5/2024 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/19/2024 Partial Approval JACOB MYERS
Wood Frame 8/30/2024 Partial Inspection DAVID BURKHEAD
Pre-Inspection 10/7/2024 Approved RAFAEL CORTES
Interior/Exterior Lathing 11/25/2024 Not Ready for Inspection RAFAEL CORTES
Interior/Exterior Lathing 12/5/2024 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 12/11/2024 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 12/16/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 1/7/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 1/24/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 1/24/2025 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 2/3/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 2/3/2025 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 2/7/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 2/7/2025 Partial Approval EDWIN GREGORYONA
Insulation 2/18/2025 Partial Approval RAFAEL CORTES
Insulation 2/19/2025 No Access for Inspection RAFAEL CORTES
Interior/Exterior Lathing 2/20/2025 No Access for Inspection RAFAEL CORTES
Interior/Exterior Lathing 2/21/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 3/17/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 4/2/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 4/10/2025 Partial Approval RAFAEL CORTES
Special/Order Compliance 6/20/2025 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/14/2025 Not Ready for Inspection EDWIN GREGORYONA
Special/Order Compliance 7/18/2025 Partial Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 8/28/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 9/19/2025 Not Ready for Inspection RAFAEL CORTES
Posting Pre-Inspection 10/7/2025 Not Ready for Inspection EDWIN GREGORYONA
Posting Pre-Inspection 10/16/2025 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 10/30/2025 No Access for Inspection RAFAEL CORTES
Footing/Foundation/Slab 10/31/2025 Partial Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 11/20/2025 Partial Approval RAFAEL CORTES
Final 2/24/2026 Not Ready for Inspection RAFAEL CORTES
Green Building Final 2/24/2026 Partial Approval RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 2/24/2026 SGSOV Approved RAFAEL CORTES
Smoke Detectors 2/24/2026 Approved RAFAEL CORTES
Final 3/25/2026 Conditional Approval RAFAEL CORTES
Green Building Final 3/25/2026 Approved RAFAEL CORTES