4701 W ADAMS BLVD 90016
Certificate Information: 4701 W ADAMS BLVD 90016
- Application / Permit
- 22016-10000-24817
- Plan Check / Job No.
- B22LA16457
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (11) Hotel
- Work Description
- NFPA 13R FIRE SPRINKLERS REQUIRED. PROJECT HOMEKEY: MULTIFAMILY HOUSING PROGRAM PER GCS 50675.1.3. CHANGE OF USE FROM (E) NON-TRANSIENT HOTEL (R-2) TO MULTIFAMILY HOUSING, 100% AFFORDABLE, WITHIN (E) 2-STORY TYPE VB BUILDING. CONVERT PARKING GARAGE TO SUPPORTIVE OFFICE.
- Permit Issued
- Issued on 5/13/2024
- Issuing Office
- Current Status
- Issued on 5/13/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | KEVIN MORALES |
| Corrections Issued | 8/29/2022 | KEVIN MORALES |
| Quality Review Completed | 9/1/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 10/27/2022 | KEVIN MORALES |
| Plan Check Approved | 10/19/2023 | KEVIN MORALES |
| Issued | 5/13/2024 | APPLICANT |
| TCO Issued (Expire Date: 09-22-2026) | 3/26/2026 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 9/3/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 9/22/2022 | EILEEN HUNT |
| Community Plan Implem. Overlay | Cleared | 10/4/2022 | KYLE WINSTON |
| Historic Resource Verification | Cleared | 10/7/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 11/15/2022 | GRACIELA ACOSTA |
| Green Code | Cleared | 11/23/2022 | AARON COSTA |
| SB8 RUD | Cleared | 12/19/2022 | JESSICA WANG |
| Fire Marshal Fire Life Safety | Cleared | 1/12/2023 | WILLIAM JOHNS |
| Miscellaneous | Cleared | 4/13/2023 | MARITZA PRZEKOP |
| Permanent Supportive Housing | Cleared | 4/13/2023 | MARITZA PRZEKOP |
| Low Impact Development | Cleared | 6/19/2023 | MARTIN FRAGOSO |
| Public Housing | Cleared | 9/21/2023 | GUS VINDELL |
| DAS Clearance | Cleared | 10/16/2023 | Rodolfo Arias |
Contact Information
| Contractor | Level Construction Group Inc; Lic. No.: 991265-B | , |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: C40985 | 30423 CANWOOD ST STE 223 AGOURA HILLS, CA 91301 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/3/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 7/3/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 7/5/2024 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/19/2024 | Partial Approval | JACOB MYERS |
| Wood Frame | 8/30/2024 | Partial Inspection | DAVID BURKHEAD |
| Pre-Inspection | 10/7/2024 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 11/25/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Interior/Exterior Lathing | 12/5/2024 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 12/11/2024 | Partial Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 12/16/2024 | Partial Approval | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 1/7/2025 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 1/24/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 1/24/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Light Gage Steel Frame | 2/3/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 2/3/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Light Gage Steel Frame | 2/7/2025 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 2/7/2025 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 2/18/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 2/19/2025 | No Access for Inspection | RAFAEL CORTES |
| Interior/Exterior Lathing | 2/20/2025 | No Access for Inspection | RAFAEL CORTES |
| Interior/Exterior Lathing | 2/21/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 3/17/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 4/2/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 4/10/2025 | Partial Approval | RAFAEL CORTES |
| Special/Order Compliance | 6/20/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 7/14/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Special/Order Compliance | 7/18/2025 | Partial Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 8/28/2025 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 9/19/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Posting Pre-Inspection | 10/7/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Posting Pre-Inspection | 10/16/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 10/30/2025 | No Access for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 10/31/2025 | Partial Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 11/20/2025 | Partial Approval | RAFAEL CORTES |
| Final | 2/24/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 2/24/2026 | Partial Approval | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 2/24/2026 | Approved | RAFAEL CORTES |
| Final | 3/25/2026 | Conditional Approval | RAFAEL CORTES |
| Green Building Final | 3/25/2026 | Approved | RAFAEL CORTES |