1600 S MAIN ST 90291

Certificate Information: 1600 S MAIN ST 90291

Application / Permit
22016-10000-24698
Plan Check / Job No.
B22LA16384
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Tenant improvement of existing 7,330 s.f. 2-story office building w/ mezzanine and new rooftop deck w/ Exterior: - (N) staircase from 2nd floor to low & high roofs Interior: - Non-bearing interior partitions, new lighting fixture and new HVAC & plumbing under separate permit, Removal of circular stair , Structural maintenance of floors & roof new bathrooms/kitchen/break room and office spaces throughout
Permit Issued
Issued on 12/7/2022
Issuing Office
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 PETER MOSESIAN
Corrections Issued 8/29/2022 PETER MOSESIAN
Quality Review Completed 9/7/2022 OMID HEDAYAT
Plan Check Approved 12/6/2022 PETER MOSESIAN
Issued 12/7/2022 APPLICANT
CofO in Progress 5/20/2024 FARHAD DADBIN
Permit Finaled 5/29/2024 DAVID TSAU
CofO Issued 5/29/2024 DAVID TSAU
Permit Finaled 5/29/2024 DAVID TSAU

Permit Application Clearance Information

Hist. Property Cntrct Mgr Appr Cleared 9/14/2022 MELISSA JONES
ZI Cleared 9/14/2022 MELISSA JONES
ZA Case Cleared 9/16/2022 DANIEL CORONADO
ZA Case Cleared 9/16/2022 DANIEL CORONADO
ZA Case Cleared 9/16/2022 DANIEL CORONADO
ZA Case Cleared 9/16/2022 DANIEL CORONADO
ZA Case Cleared 9/16/2022 DANIEL CORONADO
ZA Case Cleared 9/16/2022 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 9/21/2022 JENSON LEE
Sewer availability Cleared 9/21/2022 JENSON LEE
Coastal Zone Cleared 11/2/2022 SHASHA YU
DAS Clearance Cleared 11/22/2022 ELIZABETH TOMS
Green Code Cleared 11/29/2022 AARON COSTA
Specific Plan Cleared 11/30/2022 IRA BROWN
ZI Cleared 11/30/2022 IRA BROWN

Contact Information

Architect Paszterko,, Andrew Elemer; Lic. No.: C12253 2055 N ALVARADO ST      LOS ANGELES, CA 90039
Contractor Kcc Design Build, Inc; Lic. No.: 932319-B       ,
Engineer Ghanim,, Husam; Lic. No.: S5689 1594 CASITAS AVENUE      PASADENA, CA 91103

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/12/2023 Partial Inspection SORIN CIRSTOIU
Deputy Drilled-In Anchors 1/25/2023 Approved FARHAD DADBIN
Footing/Foundation/Slab 1/30/2023 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 1/31/2023 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 2/23/2023 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 3/16/2023 Conditional Approval SORIN CIRSTOIU
Pre-Inspection 4/17/2023 Partial Inspection SORIN CIRSTOIU
Deputy Steel/Welding 4/20/2023 Partial Approval SORIN CIRSTOIU
Deputy Other (see comments) 5/5/2023 Conditional Approval FARHAD DADBIN
Deputy Reinf. Concrete 5/5/2023 Conditional Approval FARHAD DADBIN
Footing/Foundation/Slab 5/30/2023 Partial Approval FARHAD DADBIN
Insulation 6/2/2023 Partial Approval FARHAD DADBIN
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Partial Inspection AMANUEL BERHE
Insulation 6/15/2023 Partial Inspection AMANUEL BERHE
Deputy Wood Construction 7/19/2023 Conditional Approval FARHAD DADBIN
Green Building Rough 7/27/2023 Not Ready for Inspection FARHAD DADBIN
METHANE-Rough 7/27/2023 Not Ready for Inspection FARHAD DADBIN
Structural Steel Frame 7/27/2023 Not Ready for Inspection FARHAD DADBIN
Wood Frame 7/27/2023 Not Ready for Inspection FARHAD DADBIN
Insulation 8/4/2023 Partial Approval FARHAD DADBIN
Drywall Nailing 8/15/2023 Partial Approval FARHAD DADBIN
Drywall Nailing 9/7/2023 Partial Approval FARHAD DADBIN
Interior/Exterior Lathing 9/27/2023 Partial Approval FARHAD DADBIN
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Approved FARHAD DADBIN
Green Building Rough 10/10/2023 Approved FARHAD DADBIN
Insulation 10/10/2023 Approved FARHAD DADBIN
Light Gage Steel Frame 10/10/2023 Conditional Approval FARHAD DADBIN
METHANE-Rough 10/10/2023 Approved FARHAD DADBIN
Structural Steel Frame 10/10/2023 Partial Approval FARHAD DADBIN
Drywall Nailing 10/24/2023 Partial Approval FARHAD DADBIN
Drywall Nailing 10/30/2023 Partial Approval FARHAD DADBIN
Deputy Drilled-In Anchors 12/1/2023 Conditional Approval FARHAD DADBIN
Reinforced Masonry Frame 12/5/2023 Partial Approval FARHAD DADBIN
Reinforced Masonry Frame 12/6/2023 Not Ready for Inspection FARHAD DADBIN
Masonry Wall/Backfill 12/18/2023 Not Ready for Inspection CASIMIR BRITTON
Reinforced Masonry Frame 12/20/2023 Approved AMANUEL BERHE
Wall Anchors 12/20/2023 Approved AMANUEL BERHE
Final 1/25/2024 Corrections Issued FARHAD DADBIN
Green Building Final 1/25/2024 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 1/25/2024 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 1/25/2024 Not Ready for Inspection FARHAD DADBIN
Structural Steel Frame 1/25/2024 Not Ready for Inspection FARHAD DADBIN
Deputy Steel/Welding 3/14/2024 Conditional Approval FARHAD DADBIN
Deputy Other (see comments) 3/22/2024 Conditional Approval GRANT WOODS
Final 3/22/2024 Corrections Issued GRANT WOODS
Green Building Final 3/22/2024 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Not Ready GRANT WOODS
Smoke Detectors 3/22/2024 Not Ready for Inspection GRANT WOODS
Structural Steel Frame 3/22/2024 Not Ready for Inspection GRANT WOODS
Wood Frame 3/29/2024 Partial Approval FARHAD DADBIN
Final 5/10/2024 Not Ready for Inspection FARHAD DADBIN
Green Building Final 5/10/2024 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved FARHAD DADBIN
Smoke Detectors 5/10/2024 Approved FARHAD DADBIN
Structural Steel Frame 5/10/2024 Not Ready for Inspection FARHAD DADBIN
Final 5/20/2024 OK to Issue CofO FARHAD DADBIN
Structural Steel Frame 5/20/2024 Approved FARHAD DADBIN