1600 S MAIN ST 90291
Certificate Information: 1600 S MAIN ST 90291
- Application / Permit
- 22016-10000-24698
- Plan Check / Job No.
- B22LA16384
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Tenant improvement of existing 7,330 s.f. 2-story office building w/ mezzanine and new rooftop deck w/ Exterior: - (N) staircase from 2nd floor to low & high roofs Interior: - Non-bearing interior partitions, new lighting fixture and new HVAC & plumbing under separate permit, Removal of circular stair , Structural maintenance of floors & roof new bathrooms/kitchen/break room and office spaces throughout
- Permit Issued
- Issued on 12/7/2022
- Issuing Office
- Current Status
- CofO Issued on 5/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | PETER MOSESIAN |
| Corrections Issued | 8/29/2022 | PETER MOSESIAN |
| Quality Review Completed | 9/7/2022 | OMID HEDAYAT |
| Plan Check Approved | 12/6/2022 | PETER MOSESIAN |
| Issued | 12/7/2022 | APPLICANT |
| CofO in Progress | 5/20/2024 | FARHAD DADBIN |
| Permit Finaled | 5/29/2024 | DAVID TSAU |
| CofO Issued | 5/29/2024 | DAVID TSAU |
| Permit Finaled | 5/29/2024 | DAVID TSAU |
Permit Application Clearance Information
| Hist. Property Cntrct Mgr Appr | Cleared | 9/14/2022 | MELISSA JONES |
| ZI | Cleared | 9/14/2022 | MELISSA JONES |
| ZA Case | Cleared | 9/16/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 9/16/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 9/16/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 9/16/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 9/16/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 9/16/2022 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2022 | JENSON LEE |
| Sewer availability | Cleared | 9/21/2022 | JENSON LEE |
| Coastal Zone | Cleared | 11/2/2022 | SHASHA YU |
| DAS Clearance | Cleared | 11/22/2022 | ELIZABETH TOMS |
| Green Code | Cleared | 11/29/2022 | AARON COSTA |
| Specific Plan | Cleared | 11/30/2022 | IRA BROWN |
| ZI | Cleared | 11/30/2022 | IRA BROWN |
Contact Information
| Architect | Paszterko,, Andrew Elemer; Lic. No.: C12253 | 2055 N ALVARADO ST LOS ANGELES, CA 90039 |
| Contractor | Kcc Design Build, Inc; Lic. No.: 932319-B | , |
| Engineer | Ghanim,, Husam; Lic. No.: S5689 | 1594 CASITAS AVENUE PASADENA, CA 91103 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/12/2023 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 1/25/2023 | Approved | FARHAD DADBIN |
| Footing/Foundation/Slab | 1/30/2023 | Partial Approval | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 1/31/2023 | Approved | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 2/23/2023 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Steel/Welding | 3/16/2023 | Conditional Approval | SORIN CIRSTOIU |
| Pre-Inspection | 4/17/2023 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Steel/Welding | 4/20/2023 | Partial Approval | SORIN CIRSTOIU |
| Deputy Other (see comments) | 5/5/2023 | Conditional Approval | FARHAD DADBIN |
| Deputy Reinf. Concrete | 5/5/2023 | Conditional Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 5/30/2023 | Partial Approval | FARHAD DADBIN |
| Insulation | 6/2/2023 | Partial Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Partial Inspection | AMANUEL BERHE |
| Insulation | 6/15/2023 | Partial Inspection | AMANUEL BERHE |
| Deputy Wood Construction | 7/19/2023 | Conditional Approval | FARHAD DADBIN |
| Green Building Rough | 7/27/2023 | Not Ready for Inspection | FARHAD DADBIN |
| METHANE-Rough | 7/27/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Structural Steel Frame | 7/27/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 7/27/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 8/4/2023 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 8/15/2023 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 9/7/2023 | Partial Approval | FARHAD DADBIN |
| Interior/Exterior Lathing | 9/27/2023 | Partial Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Approved | FARHAD DADBIN |
| Green Building Rough | 10/10/2023 | Approved | FARHAD DADBIN |
| Insulation | 10/10/2023 | Approved | FARHAD DADBIN |
| Light Gage Steel Frame | 10/10/2023 | Conditional Approval | FARHAD DADBIN |
| METHANE-Rough | 10/10/2023 | Approved | FARHAD DADBIN |
| Structural Steel Frame | 10/10/2023 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 10/24/2023 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 10/30/2023 | Partial Approval | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 12/1/2023 | Conditional Approval | FARHAD DADBIN |
| Reinforced Masonry Frame | 12/5/2023 | Partial Approval | FARHAD DADBIN |
| Reinforced Masonry Frame | 12/6/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Masonry Wall/Backfill | 12/18/2023 | Not Ready for Inspection | CASIMIR BRITTON |
| Reinforced Masonry Frame | 12/20/2023 | Approved | AMANUEL BERHE |
| Wall Anchors | 12/20/2023 | Approved | AMANUEL BERHE |
| Final | 1/25/2024 | Corrections Issued | FARHAD DADBIN |
| Green Building Final | 1/25/2024 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 1/25/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Structural Steel Frame | 1/25/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Deputy Steel/Welding | 3/14/2024 | Conditional Approval | FARHAD DADBIN |
| Deputy Other (see comments) | 3/22/2024 | Conditional Approval | GRANT WOODS |
| Final | 3/22/2024 | Corrections Issued | GRANT WOODS |
| Green Building Final | 3/22/2024 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 3/22/2024 | Not Ready for Inspection | GRANT WOODS |
| Structural Steel Frame | 3/22/2024 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 3/29/2024 | Partial Approval | FARHAD DADBIN |
| Final | 5/10/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 5/10/2024 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 5/10/2024 | Approved | FARHAD DADBIN |
| Structural Steel Frame | 5/10/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 5/20/2024 | OK to Issue CofO | FARHAD DADBIN |
| Structural Steel Frame | 5/20/2024 | Approved | FARHAD DADBIN |