114 W 110TH ST 90061
Certificate Information: 114 W 110TH ST 90061
- Application / Permit
- 22016-10000-24596
- Plan Check / Job No.
- X22LA12807
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (8) Window change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council (NFRC), is required for doors and windows replaced in all residential buildings, three stories or less, per Section 150.2(b) 1B of Title 24. Fire damage repair for residential buildings only (maximum 10% of replacement cost of building). Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over new solid sheathing ___2___Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone (VHFHSZ). For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141(b) 2B. "Comply with Department Order effective date 11/15/2019."
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 7/26/2023
Permit Application Status History
| Issued | 8/16/2022 | APPLICANT |
| Permit Finaled | 7/26/2023 | JAMES CHAVEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Refinish Plus Inc; Lic. No.: 1050293-B | 8133 PURITAN ST DOWNEY, CA 90242 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 8/23/2022 | No Access for Inspection | NEVILLE REID |
| Smoke Detectors | 8/23/2022 | No Access for Inspection | NEVILLE REID |
| Final | 10/31/2022 | Not Ready for Inspection | JOHN KLARIN |
| Pre-Inspection | 10/31/2022 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 10/31/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 2/9/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 2/9/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 5/25/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 5/25/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 6/22/2023 | Corrections Issued | JAMES CHAVEZ |
| Smoke Detectors | 6/22/2023 | Approved | JAMES CHAVEZ |
| Final | 7/26/2023 | Permit Finaled | JAMES CHAVEZ |
| Smoke Detectors | 7/26/2023 | Approved | JAMES CHAVEZ |