1754 N NORTH MAIN ST 90031
Certificate Information: 1754 N NORTH MAIN ST 90031
- Application / Permit
- 22016-10000-24236
- Plan Check / Job No.
- B22LA16138
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Shoe Manufacturing
- Work Description
- EPLAN: Chnage of use from Dog Boarding / Breeding to "Shoe Manufacturing". Exterior building remodel, new windows, new doors and stairway. See Comment.
- Permit Issued
- Issued on 5/24/2023
- Issuing Office
- Current Status
- CofO Issued on 2/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | TSE MING HUANG |
| Corrections Issued | 9/27/2022 | TSE MING HUANG |
| Quality Review Completed | 9/29/2022 | EUGENE BARBEAU |
| Plan Check Approved | 5/24/2023 | TSE MING HUANG |
| Issued | 5/24/2023 | APPLICANT |
| CofO in Progress | 2/8/2024 | RAFAEL CORTES |
| Permit Finaled | 2/8/2024 | ERNESTO CORRAL |
| CofO Issued | 2/8/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZI | Cleared | 9/26/2022 | SHASHA YU |
| Encroachment in public way | Cleared | 12/6/2022 | JEREMY CHOK |
| Historic Resource Verification | Cleared | 12/7/2022 | GRACIELA ACOSTA |
| Redevelopment Project Area | Cleared | 12/7/2022 | GRACIELA ACOSTA |
| Sewer availability | Cleared | 12/7/2022 | WALLIE JONG |
| ZI | Cleared | 12/7/2022 | SHASHA YU |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2022 | WALLIE JONG |
| DAS Clearance | Cleared | 3/8/2023 | Samuel Gonzalez |
Contact Information
| Contractor | A A Greco, Inc; Lic. No.: 585352-B | , |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: NA43117 | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/2/2023 | Corrections Issued | RAFAEL CORTES |
| Footing/Foundation/Slab | 6/30/2023 | Approved | JULIAN CAPUCETTI |
| Deputy Wood Construction | 7/7/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Footing/Foundation/Slab | 7/7/2023 | Approved | JULIAN CAPUCETTI |
| Wood Frame | 7/7/2023 | Approved | JULIAN CAPUCETTI |
| Structural Steel Frame | 8/24/2023 | Partial Approval | JULIAN CAPUCETTI |
| Final | 11/1/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 11/1/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 11/27/2023 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 11/27/2023 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 11/27/2023 | Approved | RAFAEL CORTES |
| Final | 2/7/2024 | OK to Issue CofO | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV No Gas | RAFAEL CORTES |