4216 S REDWOOD AVE 90066

Certificate Information: 4216 S REDWOOD AVE 90066

Application / Permit
22016-10000-24133
Plan Check / Job No.
B22LA16054
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO (E) ONE STORY SINGLE FAMILY DWELLING TO CREATE A 54'-10" X 40'TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 6/12/2023
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 9/6/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 9/8/2022 OMID HEDAYAT
Applicant returned to address corrections 12/17/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 4/26/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 5/18/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 6/8/2023 SEWADA ZADOORAN MILAGARDI
Issued 6/12/2023 APPLICANT
CofO in Progress 3/12/2025 MICHAEL ALLEN
Permit Finaled 4/24/2025 RICHARD STEINBACH
CofO Issued 4/24/2025 RICHARD STEINBACH
Permit Finaled 4/24/2025 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 9/7/2022 CATHERINE ADROVER
Sewer availability Cleared 9/7/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 9/15/2022 CATHERINE ADROVER
Miscellaneous Cleared 9/22/2022 ANACANY HURTADO
Hydrant and Access approval Cleared 10/21/2022 KURT CORRAL
Trees in Parkway Cleared 1/10/2023 ADALBERTO VERA
Low Impact Development Cleared 1/24/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 2/2/2023 CATHERINE ADROVER

Contact Information

Contractor Westside Construction; Lic. No.: 852976-B       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/14/2023 Partial Inspection HERBERT GIRON
Excavation/Setback/Form/Re-Bar 11/2/2023 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 11/2/2023 Conditional Approval HERBERT GIRON
Special/Order Compliance 11/2/2023 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 11/6/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 12/22/2023 Not Ready for Inspection JESUS RODRIGUEZ
Underground Mechanical 12/22/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 12/26/2023 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 1/3/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 1/3/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/10/2024 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 1/10/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Corrections Issued JESUS RODRIGUEZ
Deputy Wood Construction 4/22/2024 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 4/29/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 7/25/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 7/25/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 8/5/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 8/5/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/27/2024 Approved JESUS PINEDA
Green Building Rough 8/27/2024 Approved JESUS PINEDA
HVAC-Rough 8/27/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 8/27/2024 Partial Approval JESUS PINEDA
Verify Sprinkler Sign Off 8/27/2024 Approved JESUS PINEDA
Insulation 9/4/2024 Corrections Issued JESUS PINEDA
Drywall Nailing 9/13/2024 Approved JESUS PINEDA
Insulation 9/13/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 10/16/2024 Approved JESUS PINEDA
Shower Pan 10/16/2024 Approved JESUS PINEDA
ELECTRICAL-Final 1/28/2025 Approved JESUS PINEDA
HVAC-Final 1/31/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 1/31/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 2/4/2025 Approved MICHAEL ALLEN
Service/Power Release 2/4/2025 Approved MICHAEL ALLEN
HVAC-Final 2/7/2025 Approved BOBBY KEY
Final 3/11/2025 OK to Issue CofO MICHAEL ALLEN
Green Building Final 3/11/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 3/11/2025 SGSOV Not Required MICHAEL ALLEN
Smoke Detectors 3/11/2025 Approved MICHAEL ALLEN