3360 N TYBURN ST 90039
Certificate Information: 3360 N TYBURN ST 90039
- Application / Permit
- 22016-10000-24063
- Plan Check / Job No.
- B22LA15992
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD BEDROOM AND REMODEL INTERIOR.
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/24/2023
Permit Application Status History
| Plan Check Approved | 8/11/2022 | DANIEL SANJUAN |
| Issued | 8/11/2022 | APPLICANT |
| Permit Finaled | 1/23/2023 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/6/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 9/9/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 9/14/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/16/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/16/2022 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/19/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/26/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/26/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/6/2022 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 10/12/2022 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/12/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 11/22/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 11/22/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 12/1/2022 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 12/1/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 12/14/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Gas Test | 12/27/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 12/27/2022 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 12/29/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 1/3/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 1/17/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 1/17/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 1/23/2023 | Permit Finaled | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/23/2023 | Approved | HAMIK HARTOUNIAN |