3814 W SUNSET BLVD 90026
Certificate Information: 3814 W SUNSET BLVD 90026
- Application / Permit
- 22016-10000-24058
- Plan Check / Job No.
- B22LA15989
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Cafe
- Work Description
- CHANGE OF USE FORM (E) RETAIL SPACE INTO CAFE PER ZA-2021-10095-CUB. the hours of operation from 7am to 11 pm.
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/17/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/19/2022 | APPLICANT |
| Plan Check Approved | 3/30/2023 | AUNG SOE |
| Issued | 4/17/2023 | APPLICANT |
| TCO Issued (Expire Date: 05-14-2024) | 11/16/2023 | ADAM BURGESS |
| CofO in Progress | 4/19/2024 | RAFAEL CORTES |
| Permit Finaled | 4/19/2024 | RAFAEL ESPINOZA |
| CofO Issued | 4/19/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 4/19/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2022 | WALLIE JONG |
| Sewer availability | Cleared | 12/29/2022 | WALLIE JONG |
| Food Service Establishment | Cleared | 2/10/2023 | RAMESHBHAIR PATEL |
| ZA Case | Cleared | 3/14/2023 | OMAR GALICIA |
| "Q" conditions | Cleared | 3/22/2023 | ANACANY HURTADO |
| Comm Cor/Mini-Mall | Cleared | 3/22/2023 | ANACANY HURTADO |
| Food establishment approval | Cleared | 3/30/2023 | LACDHS APPROVED |
Contact Information
| Architect | Kapeller,, Christoph; Lic. No.: C29371 | 902 S CURSON AVENUE LOS ANGELES, CA 90036 |
| Contractor | Charger Construction & Design A; Lic. No.: 998147-B | 1819 S E 17TH STREET STE 1209 FORT LAUDERDALE, FL 33316 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2023 | Approved | TIMOTHY POWELL |
| Masonry Wall/Backfill | 8/24/2023 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 9/12/2023 | No Access for Inspection | VAHE KELEDJIAN |
| Drywall Nailing | 9/15/2023 | Approved | MARTIN TAVITIAN |
| Final | 11/6/2023 | Corrections Issued | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 11/6/2023 | Approved | KATY RAMIREZ |
| Final | 11/9/2023 | Partial Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV No Gas | KATY RAMIREZ |
| Final | 4/9/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 4/16/2024 | Approved | RAFAEL CORTES |
| Final | 4/18/2024 | OK to Issue CofO | RAFAEL CORTES |