6428 W 5TH ST 90048

Certificate Information: 6428 W 5TH ST 90048

Application / Permit
22016-10000-23989
Plan Check / Job No.
B22LA15940
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A)). WORK PER ENGINEER OF RECORD
Permit Issued
Issued on 2/23/2023
Issuing Office
Current Status
CofO Issued on 4/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2022 APPLICANT
Assigned to Plan Check Engineer 8/10/2022 AUNG SOE
Corrections Issued 8/10/2022 AUNG SOE
Applicant returned to address corrections 10/21/2022 RAHEL BEYENE
Plan Check Approved 2/13/2023 ADAM HEGAZI
Issued 2/23/2023 APPLICANT
CofO in Progress 3/24/2025 EVAN COOPER
CofO Issued 4/9/2025 RICHARD STEINBACH
Permit Finaled 4/9/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/30/2022 JEANETTE VONG
Sewer availability Cleared 8/30/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/31/2022 JEANETTE VONG
CPC Cleared 9/2/2022 SPENCER WEJROWSKI
Construction near power lines Cleared 2/13/2023 TINA MIRANDA

Contact Information

Contractor Poolside Gardens Incorporated; Lic. No.: 1075958-C27 2919 MAIDEN LN      ALTADENA, CA 91001

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/25/2023 Approved JEREMY TODD
Underground Mechanical 5/25/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 10/19/2023 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 10/19/2023 Partial Approval MEL KHACHATOURIAN
Green Building Rough 10/19/2023 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Rough 10/19/2023 Approved MEL KHACHATOURIAN
PLUMBING-Rough 10/19/2023 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 3/19/2024 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 3/21/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 5/8/2024 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 5/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
Gas Test 5/8/2024 Approved MEL KHACHATOURIAN
Green Building Rough 5/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 5/8/2024 Partial Approval MEL KHACHATOURIAN
Sewer 5/8/2024 Approved MEL KHACHATOURIAN
Wood Frame 5/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
Pre-Inspection 8/16/2024 Approved MEL KHACHATOURIAN
Deputy Wood Construction 11/4/2024 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 11/6/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 11/6/2024 Approved BOBBY KEY
HVAC-Rough 11/6/2024 Approved BOBBY KEY
PLUMBING-Rough 11/6/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/7/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 11/14/2024 Approved MEL KHACHATOURIAN
Green Building Rough 11/14/2024 Approved MEL KHACHATOURIAN
Wood Frame 11/14/2024 Approved MEL KHACHATOURIAN
Insulation 11/18/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 11/18/2024 Partial Approval MEL KHACHATOURIAN
Drywall Nailing 11/21/2024 Approved MEL KHACHATOURIAN
Shower Pan 11/21/2024 Not Ready for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 11/25/2024 Approved MEL KHACHATOURIAN
Shower Pan 11/25/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 2/26/2025 Corrections Issued SEAN HAUPT
Final 2/26/2025 Corrections Issued SEAN HAUPT
HVAC-Final 2/26/2025 Corrections Issued SEAN HAUPT
PLUMBING-Final 2/26/2025 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Approved SEAN HAUPT
ELECTRICAL-Final 3/24/2025 Approved EVAN COOPER
Final 3/24/2025 OK to Issue CofO EVAN COOPER
Green Building Final 3/24/2025 Approved EVAN COOPER
HVAC-Final 3/24/2025 Approved EVAN COOPER
Smoke Detectors 3/24/2025 Approved EVAN COOPER