135 W VIA MARINA 90292

Certificate Information: 135 W VIA MARINA 90292

Application / Permit
22016-10000-23904
Plan Check / Job No.
B22LA15875
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Renovation of existing 3-story single family residence: interior basement renovation w/ new swimming pool, exterior window/door replacement, removal of existing arch. features with new arch. features added, new solar structure over existing rooftop w/ photovoltaic & solar hot water panels, and interior bathroom renovation on 2nd floor.
Permit Issued
Issued on 12/21/2022
Issuing Office
Current Status
Permit Finaled on 12/30/2024

Permit Application Status History

Submitted 8/10/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 CRYSTEL MAALOUF
Corrections Issued 9/15/2022 CRYSTEL MAALOUF
Quality Review Completed 9/19/2022 GARO TELMI
Applicant returned to address corrections 12/7/2022 CRYSTEL MAALOUF
Plan Check Approved 12/20/2022 CRYSTEL MAALOUF
Issued 12/21/2022 APPLICANT
Permit Finaled 12/27/2024 MICHAEL ALLEN

Permit Application Clearance Information

Sewer availability Cleared 9/19/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 9/22/2022 CATHERINE ADROVER
Coastal Zone Cleared 9/27/2022 RYAN LY
Miscellaneous Cleared 9/27/2022 RYAN LY
Miscellaneous Cleared 9/27/2022 RYAN LY
Miscellaneous Cleared 9/27/2022 RYAN LY
ZA Case Cleared 9/27/2022 RYAN LY
ZA Case Cleared 9/27/2022 RYAN LY
ZA Case Cleared 9/27/2022 RYAN LY
ZI Cleared 9/27/2022 RYAN LY
Specific Plan Cleared 10/3/2022 FREDDY GARCIA
Specific Plan Cleared 10/17/2022 IRA BROWN

Contact Information

Architect Mack,, Mark; Lic. No.: C17231 427 LINNIE CANAL      VENICE, CA 90291
Architect Mack,, Mark; Lic. No.: NA17231       ,
Contractor Breakform Construction Inc; Lic. No.: 1092047-B 127 ARENA STREET      EL SEGUNDO, CA 90245
Engineer Resnick,, Bruce Daniel; Lic. No.: NA3293       ,
Engineer Resnick,, Bruce Daniel; Lic. No.: S3293 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/28/2023 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/1/2023 Partial Approval EVAN COOPER
Pre-Inspection 5/1/2023 Approved EVAN COOPER
Deputy Reinf. Concrete 5/4/2023 Conditional Approval HERBERT GIRON
PLUMBING-Rough 5/9/2023 Approved EVAN COOPER
Underground Mechanical 5/9/2023 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 5/24/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 6/1/2023 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 6/2/2023 Partial Approval EVAN COOPER
PLUMBING-Rough 8/9/2023 Partial Approval JESUS RODRIGUEZ
Underground Mechanical 8/9/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/29/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/11/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 9/29/2023 Approved HERBERT GIRON
PLUMBING-Rough 10/19/2023 Approved HERBERT GIRON
Shower Pan 10/19/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 10/23/2023 Partial Approval HERBERT GIRON
HVAC-Rough 10/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 10/30/2023 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 11/2/2023 Partial Approval HERBERT GIRON
HVAC-Rough 11/6/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 11/16/2023 Approved HERBERT GIRON
HVAC-Rough 11/16/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 11/16/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 11/22/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Approved HERBERT GIRON
Verify Sprinkler Sign Off 11/22/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 12/9/2023 Approved TEMISTOCLES CAAL
Final 12/9/2023 Corrections Issued TEMISTOCLES CAAL
Insulation 12/9/2023 Approved TEMISTOCLES CAAL
Drywall Nailing 12/18/2023 Approved JESUS RODRIGUEZ
Piling/Pier/Caisson 12/18/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 7/16/2024 Partial Approval STEPHANIE SWANSON
Smoke Detectors 7/16/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 9/6/2024 Corrections Issued HERBERT GIRON
Gas Test 9/13/2024 Approved HERBERT GIRON
PLUMBING-Final 9/13/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 10/1/2024 Approved HERBERT GIRON
ELECTRICAL-Final 12/10/2024 Approved HERBERT GIRON
HVAC-Final 12/12/2024 Corrections Issued HERBERT GIRON
HVAC-Final 12/20/2024 Approved HERBERT GIRON
Final 12/24/2024 Corrections Issued MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 12/24/2024 SGSOV Approved MICHAEL ALLEN
Final 12/27/2024 Permit Finaled MICHAEL ALLEN
Notice of Violation 12/27/2024 Not Required MICHAEL ALLEN