4120 W MARATHON ST 90029
Certificate Information: 4120 W MARATHON ST 90029
- Application / Permit
- 22016-10000-23893
- Plan Check / Job No.
- B22LA15865
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Nursery School
- Work Description
- ePlan Tenant improvement to the classrooms in existing nursery school , offices, and playgrounds. New fire alarm system will be installed as part of this work and ADA accessibility for parking and toilet rooms will be upgraded. New elevator for ada access to 2nd floor will be added.
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Current Status
- Permit Finaled on 1/20/2026
Permit Application Status History
| Submitted | 8/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | JOHNNY WU |
| Corrections Issued | 9/8/2022 | JOHNNY WU |
| Quality Review Completed | 9/13/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/18/2022 | JOHNNY WU |
| Applicant returned to address corrections | 1/13/2023 | JOHNNY WU |
| Applicant returned to address corrections | 1/20/2023 | JOHNNY WU |
| Applicant returned to address corrections | 2/17/2023 | JOHNNY WU |
| Applicant returned to address corrections | 2/22/2023 | JOHNNY WU |
| Applicant returned to address corrections | 3/21/2023 | JOHNNY WU |
| Applicant returned to address corrections | 4/18/2023 | JOHNNY WU |
| Plan Check Approved | 4/18/2023 | JOHNNY WU |
| Issued | 6/29/2023 | APPLICANT |
| Permit Finaled | 1/20/2026 | RONALD JIMENEZ |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/19/2022 | RUBEN VASQUEZ |
| Prkng lot landscape/Water mgmt | Cleared | 9/19/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/19/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/19/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/19/2022 | RUBEN VASQUEZ |
| Grading Pre-Inspection | Cleared | 9/21/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 9/26/2022 | DYLAN LAWRENCE |
| ZI | Cleared | 9/26/2022 | DYLAN LAWRENCE |
| Green Code | Cleared | 10/25/2022 | AARON COSTA |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 12/9/2022 | KURT CORRAL |
| Fire Marshal Fire Life Safety | Cleared | 3/1/2023 | RONILO MULAWIN |
| Low Impact Development | Cleared | 3/12/2023 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/16/2023 | TREVOR QUAN |
| DAS Clearance | Cleared | 4/6/2023 | Hernan Arreola |
Contact Information
| Architect | Leu,, Mun C; Lic. No.: NA19763 | , |
| Contractor | The Nazerian Group; Lic. No.: 787198-B | , |
| Engineer | Costa,, Orlando Sarmiento; Lic. No.: S2285 | 1543 WEST GARVEY AVENUE WEST COVINA, CA 91790 |
| Engineer | Govil,, Sanjay; Lic. No.: GE2382 | 4 TULAROSA COURT ALISO VIEJO, CA 92656 |
| Engineer | Shwe,, James Hla; Lic. No.: M26903 | 17711 ARVIDA DRIVE GRANADA HILLS, CA 91344 |
| Engineer | Tran,, Thomas Minh; Lic. No.: C82464 | 919 W. GLENOAKS BLVD., 2ND FLOOR GLENDALE, CA 91202 |
| Landscape Architect | Simon,, David L; Lic. No.: LA1150 | 6114 LAUREL GROVE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/11/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Pre-Inspection | 7/13/2023 | Approved | RONALD JIMENEZ |
| Structural Steel Frame | 8/29/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 9/5/2023 | Partial Approval | JULIAN CAPUCETTI |
| Drywall Nailing | 9/8/2023 | Partial Approval | TIMOTHY POWELL |
| Grading Pre-Inspection | 9/19/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 10/6/2023 | Partial Approval | RONALD JIMENEZ |
| Footing/Foundation/Slab | 10/6/2023 | Partial Approval | RONALD JIMENEZ |
| Special/Order Compliance | 10/10/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Special/Order Compliance | 10/11/2023 | Partial Inspection | ALFREDO LOPEZ |
| Light Gage Steel Frame | 12/5/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 12/7/2023 | Partial Approval | RONALD JIMENEZ |
| Footing/Foundation/Slab | 12/7/2023 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 12/7/2023 | Partial Approval | RONALD JIMENEZ |
| Reinforced Concrete Frame | 12/7/2023 | Partial Approval | RONALD JIMENEZ |
| Pre-Inspection | 12/14/2023 | Approved | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 12/28/2023 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/2/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Wood Frame | 1/2/2024 | Approved | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/4/2024 | Approved | JACOB MYERS |
| T-Bar Ceiling | 3/1/2024 | Approved | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 4/12/2024 | Partial Approval | RAFAEL CORTES |
| Special/Order Compliance | 6/5/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 12/8/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Final | 12/8/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Rough | 12/8/2025 | Approved | LUIS CCAMACHO |
| Reinforced Masonry Frame | 12/8/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 12/8/2025 | Approved | LUIS CCAMACHO |
| Final | 1/20/2026 | Permit Finaled | RONALD JIMENEZ |
| Green Building Final | 1/20/2026 | Approved | RONALD JIMENEZ |
| Reinforced Masonry Frame | 1/20/2026 | Approved | RONALD JIMENEZ |