1440 W 69TH ST 90047

Certificate Information: 1440 W 69TH ST 90047

Application / Permit
22016-10000-23876
Plan Check / Job No.
B22LA15850
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED NEW CONSTRUCTIONADU PER ORDINANCE AND LAMC 12.22 A33(c)&(d) , ALL WORK DONE PER WFPP
Permit Issued
Issued on 8/24/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 KHUONG TRUONG
Corrections Issued 8/14/2022 KHUONG TRUONG
Building Plans Picked Up 8/19/2022 APPLICANT
Applicant returned to address corrections 9/16/2022 MINA HABILI
Applicant returned to address corrections 9/19/2022 FERNANDO FLORES
Applicant returned to address corrections 4/25/2023 LUKE GONZALES
Applicant returned to address corrections 8/17/2023 DANIEL SMILEY
Plan Check Approved 8/24/2023 DANIEL SANJUAN
Issued 8/24/2023 APPLICANT
CofO in Progress 5/1/2025 BARRY HACHE
Permit Finaled 5/3/2025 DEROLD HAUFF
CofO Issued 5/3/2025 DEROLD HAUFF
Permit Finaled 5/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/16/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 9/16/2022 AMAAN MALIK
Sewer availability Cleared 9/16/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 4/18/2023 CELINA MORENO
Construction near power lines Cleared 8/11/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/23/2024 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 2/27/2024 Corrections Issued RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 3/12/2024 Partial Inspection DAVID FEILER
Underground Mechanical 3/12/2024 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 3/15/2024 Approved DAVID FEILER
Footing/Foundation/Slab 3/15/2024 Conditional Approval DAVID FEILER
Underground Mechanical 3/15/2024 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 7/19/2024 No Access for Inspection DAVID FEILER
Green Building Rough 7/19/2024 No Access for Inspection DAVID FEILER
Verify Sprinkler Sign Off 7/19/2024 No Access for Inspection DAVID FEILER
Wood Frame 7/19/2024 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 8/27/2024 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/27/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 8/27/2024 Not Ready for Inspection CRAIG DAVIS
Verify Sprinkler Sign Off 8/27/2024 Not Ready for Inspection CRAIG DAVIS
Wood Frame 8/27/2024 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Partial Approval CRAIG DAVIS
Deputy Wood Construction 9/12/2024 Conditional Approval CRAIG DAVIS
Deputy Wood Construction 9/30/2024 Conditional Approval CRAIG DAVIS
BUILDING-Rough-Frame 10/4/2024 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Partial Approval CRAIG DAVIS
Green Building Rough 10/4/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 10/4/2024 Not Ready for Inspection CRAIG DAVIS
Verify Sprinkler Sign Off 10/4/2024 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 10/16/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 10/16/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 10/16/2024 Approved CRAIG DAVIS
PLUMBING-Rough 10/16/2024 Not Ready for Inspection CRAIG DAVIS
Verify Sprinkler Sign Off 10/16/2024 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 11/5/2024 Corrections Issued CRAIG DAVIS
Rough-Elec/Plmb/HVAC 11/5/2024 Corrections Issued CRAIG DAVIS
Verify Sprinkler Sign Off 11/5/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 11/20/2024 Partial Inspection MICHAEL LEWIS
Rough-Elec/Plmb/HVAC 11/20/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 11/25/2024 Partial Inspection CRAIG DAVIS
HVAC-Rough 11/25/2024 Approved CRAIG DAVIS
Verify Sprinkler Sign Off 11/25/2024 Not Ready for Inspection CRAIG DAVIS
Insulation 12/5/2024 Approved JOHN QUINTANILLA
Service/Power Release 12/5/2024 Not Ready for Inspection JOHN QUINTANILLA
Drywall Nailing 1/17/2025 Approved BARRY HACHE
Interior/Exterior Lathing 1/17/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 4/15/2025 Not Ready for Inspection BARRY HACHE
Final 4/15/2025 Not Ready for Inspection BARRY HACHE
Green Building Final 4/15/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 4/15/2025 SGSOV Not Required BARRY HACHE
Smoke Detectors 4/15/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 4/24/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 4/24/2025 Approved SABAS ALONSO
Final 4/24/2025 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 4/24/2025 Approved SABAS ALONSO
Green Building Final 4/24/2025 Approved SABAS ALONSO
HVAC-Final 4/24/2025 Approved SABAS ALONSO
PLUMBING-Final 4/24/2025 Approved SABAS ALONSO
Service/Power Release 4/24/2025 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 4/24/2025 Approved SABAS ALONSO
Verify Sprinkler Sign Off 4/24/2025 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 5/1/2025 Approved BARRY HACHE
Final 5/1/2025 OK to Issue CofO BARRY HACHE
Service/Power Release 5/1/2025 Approved BARRY HACHE