8015 S HOLY CROSS PL 90045
Certificate Information: 8015 S HOLY CROSS PL 90045
- Application / Permit
- 22016-10000-23861
- Plan Check / Job No.
- B22LA15836
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1. Convert detached garage to ADU
- Permit Issued
- Issued on 1/9/2023
- Issuing Office
- Current Status
- CofO Issued on 8/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2022 | JOE VO |
| Corrections Issued | 9/1/2022 | JOE VO |
| Quality Review Completed | 9/1/2022 | GARO TELMI |
| Plan Check Approved | 1/4/2023 | JOE VO |
| Issued | 1/9/2023 | APPLICANT |
| CofO in Progress | 8/28/2024 | BOBBY KEY |
| Permit Finaled | 8/28/2024 | RICHARD STEINBACH |
| CofO Issued | 8/28/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/28/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/14/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 11/1/2022 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 11/16/2022 | ROBERT SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/11/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 10/11/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 10/11/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 11/9/2023 | Partial Approval | BOBBY KEY |
| Sewer | 11/9/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 11/9/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 12/1/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/7/2023 | Corrections Issued | BOBBY KEY |
| Insulation | 12/7/2023 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 12/7/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/3/2024 | Conditional Approval | BOBBY KEY |
| Green Building Rough | 1/3/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/11/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 1/11/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/11/2024 | Approved | BOBBY KEY |
| Shower Pan | 1/11/2024 | Approved | BOBBY KEY |
| Final | 8/27/2024 | OK to Issue CofO | BOBBY KEY |
| Green Building Final | 8/27/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 8/27/2024 | Approved | BOBBY KEY |