12427 W SUNSET BLVD 90049

Certificate Information: 12427 W SUNSET BLVD 90049

Application / Permit
22016-10000-23759
Plan Check / Job No.
B22LA15752
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXTERIOR AND INTERIOR REMODEL TO EXISTING 2 STORY SINGLE FAMILY DEWLLING WITH ATTACHED CARPORT. (no change in floor area, height)
Permit Issued
Issued on 9/20/2022
Issuing Office
Current Status
Permit Finaled on 3/7/2023

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 AUNG SOE
Corrections Issued 8/16/2022 AUNG SOE
Plan Check Approved 8/30/2022 STANLEY RAAP
Issued 9/20/2022 APPLICANT
Building Plans Picked Up 9/21/2022 APPLICANT
Permit Finaled 3/6/2023 MICHAEL PELHAM

Permit Application Clearance Information

ZA Case Cleared 8/16/2022 MAXFIELD VERMY
Grading Pre-Inspection Cleared 8/19/2022 KIRK LINKLATER

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Williamson John Construction Inc; Lic. No.: 451421-B 8723 BLERIOT AVE      LOS ANGELES, CA 90045

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/9/2022 Corrections Issued JUAN VALENZUELA
Deputy Reinf. Concrete 11/9/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 11/9/2022 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 11/17/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 11/17/2022 Partial Approval JUAN VALENZUELA
Shower Pan 11/28/2022 Partial Approval KENNETH NAGLE
ELECTRICAL-Rough 12/6/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 12/6/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 12/12/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 12/13/2022 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 12/13/2022 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 12/16/2022 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 12/16/2022 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 12/21/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 12/21/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 12/21/2022 Approved JUAN VALENZUELA
Shower Pan 12/21/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 12/23/2022 Approved JUAN VALENZUELA
HVAC-Rough 12/23/2022 Approved JUAN VALENZUELA
Drywall Nailing 12/30/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/30/2022 Not Ready for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/30/2022 SGSOV Not Ready KEVIN SARGSYAN
Interior/Exterior Lathing 1/25/2023 Approved KEVIN SARGSYAN
Gas Test 2/16/2023 Approved HERBERT GIRON
Final 2/27/2023 No Access for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 2/27/2023 No Access for Inspection KEVIN SARGSYAN
Final 2/28/2023 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 2/28/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 3/3/2023 Approved KEVIN SARGSYAN
PLUMBING-Final 3/3/2023 Approved KEVIN SARGSYAN
Final 3/6/2023 Permit Finaled MICHAEL PELHAM