Work Description
RESIDENTIAL INTERIOR AND EXTERIOR REMODEL FOR KITCHEN, BATHROOMS, AND 2 SKY-HIGH WINDOW UPGRADES.
Permit Issued
Issued on 9/16/2022
Issuing Office
Current Status
Permit Finaled on 2/13/2024

Permit Application Status History

Submitted 8/5/2022 APPLICANT
Assigned to Plan Check Engineer 8/10/2022 ZAW HAN
Corrections Issued 8/16/2022 ZAW HAN
Building Plans Picked Up 8/17/2022 APPLICANT
Plan Check Approved 9/16/2022 SHANGQIN XIE
Issued 9/16/2022 APPLICANT
Permit Finaled 2/12/2024 OSVALDO PARAMO

Permit Application Clearance Information

Specific Plan Cleared 8/22/2022 NASHYA JENSEN
Grading Pre-Inspection Cleared 8/26/2022 KIRK LINKLATER

Contact Information

Contractor Williams Christopher; Lic. No.: 711380-B P O BOX 8652      LA CRESCENTA, CA 91224
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/13/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/21/2022 Approved HAMIK HARTOUNIAN
Pre-Inspection 2/1/2023 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/7/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/7/2023 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 3/15/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 3/15/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 3/30/2023 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/11/2023 Corrections Issued ALIZAH MAYAGOITIA
Insulation 4/11/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/14/2023 Partial Approval SCOTT FINNILA
Insulation 4/14/2023 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 4/24/2023 Approved SCOTT FINNILA
Deputy Wood Construction 4/24/2023 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Approved SCOTT FINNILA
Insulation 4/24/2023 Approved SCOTT FINNILA
Rough-Elec/Plmb/HVAC 4/24/2023 Approved SCOTT FINNILA
Drywall Nailing 5/4/2023 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 5/4/2023 Approved CHARLES BOGHOSKHAN
Shower Pan 5/4/2023 Approved CHARLES BOGHOSKHAN
Final 2/12/2024 Permit Finaled OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 2/12/2024 Approved OSVALDO PARAMO