5419 N WORTSER AVE 91401

Certificate Information: 5419 N WORTSER AVE 91401

Application / Permit
22016-10000-23426
Plan Check / Job No.
B22LA15512
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) 20' X 26' DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH 13'- 8 1/2" x 5'-0" ATTACHED PATIO COVER ADDITION PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/23/2023
Issuing Office
Current Status
CofO Issued on 1/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2022 APPLICANT
Assigned to Plan Check Engineer 8/31/2022 OMAR GARNICA
Corrections Issued 8/31/2022 OMAR GARNICA
Applicant returned to address corrections 1/26/2023 ALFRED RAMIREZ
Plan Check Approved 2/1/2023 OMAR GARNICA
Issued 2/23/2023 APPLICANT
CofO in Progress 11/2/2023 CHRISTOPHER ROJAS
Permit Finaled 1/3/2024 RUBEN SALAS
Permit Finaled 1/3/2024 RUBEN SALAS
CofO Issued 1/3/2024 RUBEN SALAS

Permit Application Clearance Information

Metro Rail approval Cleared 9/16/2022 OMAR GARNICA
Address approval Cleared 12/29/2022 COLIN LOREDO
Miscellaneous Cleared 12/29/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 12/29/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/23/2023 COLIN LOREDO
Sewer availability Cleared 1/23/2023 COLIN LOREDO

Contact Information

Contractor New Dawn Construction & Consulting Inc; Lic. No.: 1087088-B 1050 WEST ALAMEDA AVE STE 486      BURBANK, CA 91506

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/18/2023 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 4/26/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 4/26/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 5/3/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/11/2023 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 5/11/2023 Approved KIRK SANDERS
PLUMBING-Rough 7/3/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 7/5/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 7/12/2023 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 7/12/2023 Approved KIRK SANDERS
HVAC-Rough 7/12/2023 Approved KIRK SANDERS
PLUMBING-Rough 7/12/2023 Approved KIRK SANDERS
Insulation 7/28/2023 Partial Approval KIRK SANDERS
Insulation 8/1/2023 Partial Approval KIRK SANDERS
Deputy Wood Construction 8/2/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 8/7/2023 Not Ready for Inspection KIRK SANDERS
Drywall Nailing 8/11/2023 Conditional Approval JUAN VALENZUELA
Interior/Exterior Lathing 8/14/2023 Not Ready for Inspection KIRK SANDERS
Interior/Exterior Lathing 9/5/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 9/25/2023 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 9/27/2023 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/13/2023 Approved JUAN VALENZUELA
Final 10/23/2023 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 10/23/2023 Not Ready for Inspection KIRK SANDERS
Final 10/27/2023 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/27/2023 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 10/27/2023 Approved CHRISTOPHER ROJAS
Final 11/1/2023 OK to Issue CofO CHRISTOPHER ROJAS