5419 N WORTSER AVE 91401
Certificate Information: 5419 N WORTSER AVE 91401
- Application / Permit
- 22016-10000-23426
- Plan Check / Job No.
- B22LA15512
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 20' X 26' DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH 13'- 8 1/2" x 5'-0" ATTACHED PATIO COVER ADDITION PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/23/2023
- Issuing Office
- Current Status
- CofO Issued on 1/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2022 | OMAR GARNICA |
| Corrections Issued | 8/31/2022 | OMAR GARNICA |
| Applicant returned to address corrections | 1/26/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 2/1/2023 | OMAR GARNICA |
| Issued | 2/23/2023 | APPLICANT |
| CofO in Progress | 11/2/2023 | CHRISTOPHER ROJAS |
| Permit Finaled | 1/3/2024 | RUBEN SALAS |
| Permit Finaled | 1/3/2024 | RUBEN SALAS |
| CofO Issued | 1/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 9/16/2022 | OMAR GARNICA |
| Address approval | Cleared | 12/29/2022 | COLIN LOREDO |
| Miscellaneous | Cleared | 12/29/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 12/29/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 1/23/2023 | COLIN LOREDO |
Contact Information
| Contractor | New Dawn Construction & Consulting Inc; Lic. No.: 1087088-B | 1050 WEST ALAMEDA AVE STE 486 BURBANK, CA 91506 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/18/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 4/26/2023 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 4/26/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 5/3/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/11/2023 | Not Ready for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 5/11/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 7/3/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 7/5/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/12/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 7/12/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 7/12/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 7/12/2023 | Approved | KIRK SANDERS |
| Insulation | 7/28/2023 | Partial Approval | KIRK SANDERS |
| Insulation | 8/1/2023 | Partial Approval | KIRK SANDERS |
| Deputy Wood Construction | 8/2/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| Drywall Nailing | 8/11/2023 | Conditional Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/14/2023 | Not Ready for Inspection | KIRK SANDERS |
| Interior/Exterior Lathing | 9/5/2023 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 9/25/2023 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/27/2023 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/13/2023 | Approved | JUAN VALENZUELA |
| Final | 10/23/2023 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 10/23/2023 | Not Ready for Inspection | KIRK SANDERS |
| Final | 10/27/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/27/2023 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/27/2023 | Approved | CHRISTOPHER ROJAS |
| Final | 11/1/2023 | OK to Issue CofO | CHRISTOPHER ROJAS |